Nuzulia Khoiriyah
Universitas Islam Sultan Agung, Semarang, Indonesia

Published : 2 Documents Claim Missing Document
Claim Missing Document
Check
Articles

Found 2 Documents
Search
Journal : JISO : Journal of Industrial and Systems Optimization

ANALISIS HUMAN ERROR PADA PROSES PEMINTALAN BENANG DI RING SPINNING FRAME MENGGUNAKAN METODE HUMAN ERROR ASSESMENT AND REDUCTION TECHNIQUE (HEART) DAN ROOT CAUSE ANALYSIS (RCA) ( Studi Kasus : PT. Delta Dunia Sandang Tekstil ) Lisa Qotrunnada; Novi Marlyana; Nuzulia Khoiriyah
JISO : Journal of Industrial and Systems Optimization Vol 5, No 1 (2022): Juni 2022
Publisher : Universitas Maarif Hasyim Latif

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.51804/jiso.v5i1.47-53

Abstract

PT Delta Dunia Sandang Tekstil merupakan perusahaan yang bergerak di bidang industri tekstil, yang berfokus pada proses pemintalan benang. Penelitian ini berfokus pada proses produksi ring spinning frame. Proses produksi ring spinning frame tidak terlepas dari adanya produk cacat, jenis cacat yang terjadi seperti benang tidak rata, benang tipis, benang tebal dan benang gembos. Berdasarkan hasil observasi kesalahan dapat terjadi pada manusia ataupun pada mesin. Berdasarkan hasil perhitungan menggunakan metode HEART menunjukkan bahwa probabilitas kesalahan manusia dengan nilai HEP sebesar 0,135. Selanjutnya diterapkan metode RCA dengan bantuan tools 5 why methods untuk mencari akar penyebab masalah untuk meminimalisir terjadinya human error. Berdasarkan hasil RCA diperoleh faktor penyebab human error adalah Para operator kurang memiliki pengatahuan dan pengalaman yang cukup dalam melakukan proses penyambungan benang, operator belum terbiasa menyambung benang dari depan dan kurang memahami posisi badan dalam menyambung benang dengan benar, operator kurang fokus dan tidak teliti saat menyambung benang karena banyaknya benang yang putus, belum adanya sop perusahaan dalam hal menyambung benang secara detail, kurang training secara berkala yang dilakukan oleh perusahaan, belum terdapat prosedur disetiap line produksi untuk mengurangi kesalahan pada proses kerja, Tidak ada peringatan kesalahan menyambung benang. Berdasarkan hasil dari pengolahan data menggunakan metode HEART dan RCA didapatkan usulan perbaikan dalam proses produksi ring spinning frame yaitu perusahaan perlu memberikan training secara berkala kepada karyawan tentang bagaimana bekerja secara tepat untuk meminimalisir human eror, perusahaan perlu memberikan prosedur disetiap line produksi untuk mengurangi kesalahan pada proses kerja, perusahaan perlu membuat peringatan kepada karyawan sehingga karyawan tidak melewati batas prosedur yang ditentukan perusahaan, perusahaan perlu memberikan alat peredam kebisingan. ABSTRACT PT Delta Dunia Sandang Tekstil is a company engaged in the textile industry, which focuses on the yarn spinning process. This research focuses on the production process of ring spinning frames. The production process of ring spinning frames is inseparable from the existence of defective products, types of defects that occur such as uneven yarn, thin yarn, thick yarn and loose yarn. Based on the results of observations, errors can occur in humans or in machines. Based on the results of calculations using the HEART method, it shows that the probability of human error with the HEP value is 0.135. Furthermore, the RCA method is applied with the help of the 5 why methods tools to find the root cause of the problem to minimize the occurrence of human error. Based on the results of the RCA, the factors causing human error were the operators lacked sufficient knowledge and experience in the process of connecting threads, operators were not used to connecting threads from the front and did not understand the body position in connecting threads correctly, operators were less focused and not careful when connecting. thread due to the large number of broken threads, the absence of a company soup plan in terms of connecting threads in detail, lack of regular training carried out by the company, there is no procedure in each production line to reduce errors in the work process, There is no warning of thread connecting errors. Based on the results of data processing using the HEART and RCA methods, it is found that the proposed improvement in the ring spinning frame production process is that the company needs to provide regular training to employees on how to work properly to minimize human errors, the company needs to provide procedures in each production line to reduce errors in the process. At work, companies need to make warnings to employees so that employees do not cross the limits of the procedures specified by the company, companies need to provide noise suppression devices
ANALISIS PERCEPATAN WAKTU PADA PEKERJAAN SIPIL PROYEK PEMBANGUNAN LPG REFRIGERATED DENGAN MENGGUNAKAN METODE CRITICAL PATH METHOD (CPM) DAN TIME COST TRADE OFF (TCTO) Mohammad Shodig Burhanudin; Nuzulia Khoiriyah; Eli Mas’idah
JISO : Journal of Industrial and Systems Optimization Vol 6, No 1 (2023): Juni 2023
Publisher : Universitas Maarif Hasyim Latif

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.51804/jiso.v6i1.9-16

Abstract

Pembangunan LPG Refrigerated yang terletak di tuban, Jawa Timur saat ini sedang dalam proses pembangunan. Pengerjaan proyek direncanakan dalam waktu 399 hari dengan nilai total proyek sebesar Rp. 14.584.800.000. Selama pelaksanaan proyek sering mengalami keterlambatan aktivitas pekerjaan yang menyebabkan durasi waktu penyelesaiannya mengalami kemunduran dari jadwal yang telah ditentukan. Akibatnya terjadi penundaan waktu untuk memulai aktivitas pekerjaan berikutnya. Hal tersebut tidak hanya menambah durasi umur proyek, akan tetapi juga mengakibatkan pembengkakan anggaran biaya. Banyak faktor yang menyebabkan keterlambatan penyelesaian terhadap suatu pekerjaan meliputi penyediaan bahan baku, keadaan alam, letak geografis dan berbagai unsur lainnya. Dengan demikian perlu diadakan analisa untuk mempercepat durasi proyek, dimana pada penelitian ini akan menggunakan metode Critical Path Method (CPM) dan Time Cost Trade Off (TCTO) untuk melakukan percepatan durasi waktu pada aktivitas yang berada dijalur kritis. Hasil Perhitungan dengan metode Time Cost Trade Off didapatkan durasi dan biaya optimal proyek pembangunan LPG Refrigerated yaitu selama 364 hari dengan penambahan 1 jam lembur yang dapat mempercepat proyek hingga 35 hari dari durasi normal yaitu selama 399 hari dengan total tambahan biaya sebesar Rp. 235.580.228.ABSTRACTThe development of a Refrigerated LPG located in Tuban, East Java is currently under construction. Project work is planned within 399 days with a total project value of Rp. 14,584,800,000. During project implementation, work activities often experience delays which cause the duration of the completion time to experience a setback from the predetermined schedule. As a result, there is a time delay to start the next work activity. This not only increases the duration of the life of the project, but also results in an increase in the budget. Many factors cause delays in the completion of a work including the supply of raw materials, natural conditions, geographical location and various other elements. Thus it is necessary to carry out an analysis to accelerate the duration of the project, which in this study will use the Critical Path Method (CPM) and Time Cost Trade Off (TCTO) methods to accelerate the duration of time for activities that are on a critical path. Calculation results using the Time Cost Trade Off method obtained the optimal duration and cost of the Refrigerated LPG development project, namely for 364 days with the addition of 1 hour of overtime which can accelerate the project by up to 35 days from the normal duration, which is 399 days with a total additional cost of Rp. 235,580,228.