Power Plant
Vol 3 No 1 (2015): JURNAL POWER PLANT

Analisa Pengaruh Jumlah Pengoperasian CWP Terhadap Performa Kondensor PLTU Rembang

Andika Widya Pramono (Jurusan D3 Teknik Mesin, Sekolah Tinggi Teknik - PLN)
Gita Puspa Artiani (Jurusan Teknik Sipil, Sekolah Tinggi Teknik - PLN)
Alan Laksono (Jurusan D3 Teknik Mesin, Sekolah Tinggi Teknik - PLN)



Article Info

Publish Date
12 Dec 2019

Abstract

Heat exchanger is a device used to transfer heat from one fluid to another fluid. One in Rembang heat exchanger is a condenser. The condenser serves to condense low pressure steam turbine output by using sea water as coolant fluid. The condenser is a turbine auxiliary equipment which, if having problems then it will result in generation efficiency. In the design of the contractor takes 4 CWP to supply cooling water condenser, but the reality on the ground, only 3 CWP operated. Therefore it is necessary to know how the effects of these operations on the performance of the condenser. The method of analysis is done by calculating the performance of the condenser is based on the current operating parameters of the performance test. By knowing the conditions and the actual performance of the condenser, it will be able to increase plant efficiency.

Copyrights © 2015






Journal Info

Abbrev

powerplant

Publisher

Subject

Automotive Engineering Energy Industrial & Manufacturing Engineering Materials Science & Nanotechnology Mechanical Engineering

Description

The Scientific Journal of "Power Plant" is a collection of scientific works by lecturers, researchers, and practitioners in the field of Mechanical Engineering that have been published since September 2012. This journal is the result of scientific work, research in the fields of Energy, Materials ...