ANALISIS KINERJA WAKTU DAN BIAYA PROYEK KONSTRUKSI DENGAN METODE EARNED VALUE ANALYSIS

Andi Marini Indriani (Universitas Balikpapan)
Gunaedy Utomo (Universitas Balikpapan)
Muhammad Rizqy (Universitas Balikpapan)



Article Info

Publish Date
22 Sep 2022

Abstract

The International Airport Sultan Aji Muhammad Sulaiman (SAMS), Sepinggan Balikpapan is the gateway to East Kalimantan and is an airport with high aircraft movements every year. Periodic maintenance must be carried out to support airport performance. Runway surface overlay and paved shoulders is one of the works carried out for this purpose. In a construction project, good management is needed to control so that the project runs according to the planned time and cost. Earned Value Analysis (EVA) is one method that can be used to control projects. After analyzing using project data from week 1 to week 47, it is known that the costs incurred are greater than the budgeted value, this is indicated by the CPI value = 0.998. The implementation time is faster than the planned schedule, as seen in the SPI value of 1.142. The result of the final calculation of the project which indicates a loss and an estimated turnaround time of 65 weeks indicates a 4 week acceleration.

Copyrights © 2022






Journal Info

Abbrev

geoekonomi

Publisher

Subject

Decision Sciences, Operations Research & Management Economics, Econometrics & Finance Environmental Science Social Sciences

Description

Jurnal GeoEkonomi, terbitan ini berisi artikel ilmiah bidang Ekonomi yang diterbitkan secara berkala 6 bulanan (dua kali dalam satu tahun pada bulan Maret dan September). Terbit versi cetak kali pertama pada Bulan Maret 2010 (ISSN Print: ...