Journal of International Conference Proceedings
Vol 2, No 1 (2019): Proceedings of the 3rd International Conference of Project Management (ICPM) Bal

TIME ACCELERATION OF UNDERSTRUCTURE WORKS WITH FAST TRACK METHOD ZONING-BASED (CASE STUDY: TRANSIT ORIENTED DEVELOPMENT LIGHT RAIL TRANSIT JAKARTA PHASE I PROJECT)

Lusiana Indarwati (Universitas Indonesia)
Yusuf Latief (Universitas Indonesia)



Article Info

Publish Date
27 Apr 2019

Abstract

Light Rail Transit (LRT) Jakarta Phase I construction has a special purpose of launching Asian Games 18th on August 10th, 2018. In fact, this time cannot be achieved due to decision of design in Transit Oriented Development (TOD) building but it is a critical path of the overall schedule. Therefore, zoning is made with the fast track method. The purposes of this study are to develop dominant factors of making zoning, to develop fast track method with zoning-based and the proper form of zoning. The results are making zoning will be determined by manpower capacity and its risk and a grid-shape of zoning is a match in an acceleration of understructure work because the overall duration can reduce 41 days.

Copyrights © 2019






Journal Info

Abbrev

JICP

Publisher

Subject

Humanities Decision Sciences, Operations Research & Management Electrical & Electronics Engineering Industrial & Manufacturing Engineering Languange, Linguistic, Communication & Media

Description

JICP is proceedings series that aims to publish proceedings from conferences, in the fields of economics, business, and management research. All proceedings in this website are open access, which means the published articles are permanently free to read, download, copy, and distribute. The online ...