Ocean Engineering: Jurnal Ilmu Teknik dan Teknologi Maritim
Vol. 2 No. 4 (2023): Desember : Jurnal Ilmu Teknik dan Teknologi Maritim

Analisis Perbandingan Produktivitas Jam Kerja pada Proyek Reparasi Kapal TB. Ampenan 01 dengan Metode Critical Path Method & Critical Chain Project Management di Galangan Kapal Madura

Rizky Saputra Aminata (Institut Teknologi Adhi Tama Surabaya)
Minto Basuki (Institut Teknologi Adhi Tama Surabaya)



Article Info

Publish Date
26 Oct 2023

Abstract

This final assignment compared the results of durations in the CCPM method and the Critical Path Method (CPM) by conducting a case study of ship repairs at Galangan Kapal Madura Ltd. Initial project scheduling employed the traditional method of a Gantt chart, which was then broken down in more detail and complete relationships among activities into CPM form. The results were then compared with the duration in CCPM scheduling by eliminating multitasking and safety time for each activity as well as providing a buffer in progress. The CPM method lasted for 30 days at a cost of IDR 246,600,000.00, while the CCPM method lasted for 20 days at a cost of IDR 215,600,000.00. In conclusion, the CCPM method was the most effective.

Copyrights © 2023






Journal Info

Abbrev

ocean

Publisher

Subject

Engineering Mechanical Engineering

Description

Menyambut baik kiriman yang memberikan wawasan tentang masalah terkini dan utama yang berhubungan dengan ilmu Teknik dan Teknologi Maritim. Artikel bisa ditulis dalam bahasa Inggris atau bahasa ...