Optimasi Biaya dan Waktu Dengan Metode TCTO pada Pembangunan Casting Mechanical & Civil Work For Oil Storage And Steady Room Workshop Gresik

Endriastuti, Alia Maharani (Unknown)
Triana, Masca Indra (Unknown)



Article Info

Publish Date
22 Apr 2024

Abstract

In planning a project in addition to time and resource variables, cost variables (costs) have a very important role. This research was conducted on the construction of Casting Mechanical &; Civil Work For Oil Storage And Steady Room Workshop Gresik. The purpose of this study is to obtain more efficient optimal cost and time using the Time Cost Trade Off (TCTO) method. This research is carried out by means of compression or emphasis on activities that are on a critical task. From the results of the analysis with the alternative of crashing the addition of working hours (overtime), it was found that the duration of the crashing results for 1 hour of overtime was 175 days, 2 hours of overtime 173 days, and 3 hours of overtime 172 days. As for the crash cost, 1 hour of overtime is Rp. 3,123,406,448 while 2 hours is Rp. 3,119,117,964 and 3 hours of overtime is Rp. 3,117,248,350. Of the three durations, it produces an optimal time of 172 working days with a time efficiency of 3.37% and an optimal cost of Rp. 3,117,248,350 with a cost efficiency of 0.42% with an overtime duration of 3 hours.

Copyrights © 2024






Journal Info

Abbrev

jutin

Publisher

Subject

Decision Sciences, Operations Research & Management Energy Engineering Industrial & Manufacturing Engineering Mechanical Engineering

Description

Jurnal Teknik Industri Terintegrasi merupakan jurnal yang dikelola oleh Program Studi Teknik Industri Fakultas Sains dan Teknologi Universitas Pahlawan Tuanku Tambusai yang menjebatani para peneliti untuk mempublikasikan hasil penelitian di bidang ilmu teknik dan teknik industri mencakup proses ...