Analisis Penjadwalan Pekerjaan Tanah (Land Clearing) Pada Proyek Perumahan Bunda Asri Menggunakan Precedence Diagram Method

Rendy Yulianto Ramadhani (Unknown)



Article Info

Publish Date
11 Sep 2023

Abstract

The Bunda Jombang Housing development project is a project that has a land area of ​​31,401 hectares, where this housing development project was previously located on a former quarry land (Andim Rendy S, 2022), therefore it is necessary to carry out land work (land clearing) to restore the existing land structure. damaged as a result of previous mining activities. Researchers schedule earthworks so that there are no deviations from the planned schedule. An appropriate scheduling method is needed for efficient and effective utilization of the resources used. Research using the Precedence Diagram Method has the aim of analyzing implementation time and being able to determine effective scheduling for continuous work in housing development projects. (Author, 2021)

Copyrights © 2023






Journal Info

Abbrev

Konstruksi

Publisher

Subject

Chemical Engineering, Chemistry & Bioengineering Computer Science & IT Electrical & Electronics Engineering Engineering

Description

research journal of the Engineering Science Clump. The fields of study in this journal include the sub-groups of Civil Engineering and Spatial Planning, Industrial Engineering, Electrical and Computer Engineering, Earth and Marine ...