This research focuses on Bored pile work which is a fairly important component in the construction of bridge piers on toll road projects, especially at locations adjacent to river flows. This research aims to evaluate the implementation of Bored pile work at Pier 125 of the Harbour Road II Toll Road Development Project, focusing on implementation methodology, quality control, and identifying challenges that occurred during the construction process. The research methods used include: literature study to understand the basic principles and standards of Bored pile work; field observation conducted to document the stages of construction work implementation, starting from land preparation, drilling process, reinforcement installation, to concrete casting; and several tests conducted, such as slump test, and Pile Driving Analyzer (PDA) test.