Analisis Faktor Keterlambatan Proyek Gedung Pabrik Buduran Sidoarjo dan Rekomendasi Penyelesainnya

Kota, Aprintius Tuanah (Unknown)
Dzinnur, Cilda Thesisa Ilmawan (Unknown)
Qordhowi, Andrian Firdaus Yusuf Al (Unknown)



Article Info

Publish Date
20 Jan 2026

Abstract

The purpose of this study is to determine the optimal time for implementation and identify factors that cause delays in the construction project at the Buduran Factory Building in Sidoarjo. In this construction project, obstacles occurred that could result in material and moral losses. This study is a qualitative study using the Critical Path Method. The results of this study indicate that in the calculation of the critical path method for the Buduran Factory Building project in Sidoarjo, there are factors that can cause project delays, namely weather, materials, and a reduction in workers.

Copyrights © 2026






Journal Info

Abbrev

jutin

Publisher

Subject

Decision Sciences, Operations Research & Management Energy Engineering Industrial & Manufacturing Engineering Mechanical Engineering

Description

Jurnal Teknik Industri Terintegrasi merupakan jurnal yang dikelola oleh Program Studi Teknik Industri Fakultas Sains dan Teknologi Universitas Pahlawan Tuanku Tambusai yang menjebatani para peneliti untuk mempublikasikan hasil penelitian di bidang ilmu teknik dan teknik industri mencakup proses ...