Application of the Time Study Method to Analyze Discrepancies in Production Planning and Realization at PT XYZ

Jericho Agustino (Singaperbangsa Karawang University)
Fahriza Nurul Azizah (Industrial Engineering – Universitas Singaperbangsa Karawang)
Jeremi Jackson Tampubolon (Industrial Engineering – Universitas Singaperbangsa Karawang)
Naufal Rabbani Sumitra (Industrial Engineering – Universitas Singaperbangsa Karawang)



Article Info

Publish Date
30 Sep 2026

Abstract

This study aims to analyze the incompatibility between the planning and realization of aluminum production at PT Indoaluminium Intikarsa Industri, especially in Time Between Coil (TBC) activities that have the potential to cause production delays. The research uses a quantitative approach with a case study method through observation, time study, interviews, and documentation of production data. The data was analyzed using cycle time calculations, normal time, and standard time. The results showed that TB downtime was the dominant factor causing production delays, with a compatibility rate between the standard time and the actual time of 90%–100%. These findings can be used as a basis for evaluation to improve production process efficiency and control of working time. Thus, the time study method has proven to be effective in identifying the sources of inefficiencies and supporting increased compatibility between planning and production realization.

Copyrights © 2026






Journal Info

Abbrev

matriks

Publisher

Subject

Engineering Industrial & Manufacturing Engineering

Description

Matrik Journal is published by Industrial Engineering Department, Faculty of Engineering University of Muhammadiyah Gresik, twice a year in March and September. The purpose of this journal is to facilitate scientists, researchers and practitioners to publish original research articles or article ...