Evaluating the Operational Impact of Drive-by Loading on Spotting Time and Excavator Productivity in Open-Pit Mining

Yuni Sudarwanto (Institut Teknologi Indonesia, Indonesia)
Rulyenzi Rasyid (Institut Teknologi Indonesia, Indonesia)
Yenny Widianty (Institut Teknologi Indonesia, Indonesia)
Miftahul Fadillah (Darma Persada University, Indonesia)



Article Info

Publish Date
11 Oct 2026

Abstract

Loading and hauling operations strongly influence equipment utilization, production efficiency, and operating cost in open-pit mining. Although simulation, dispatch optimization, truck-shovel allocation, and Double Side Loading (DSL) have improved fleet performance, field evidence for Drive-by Loading (DBL) a continuous forward truck-approach strategy that targets the positioning micro-cycle at the loading point remains limited. This study evaluates DBL in an open-pit coal mine in South Kalimantan, Indonesia, using a quantitative before-and-after design involving two excavator classes and 100–110-ton rigid dump trucks. The screened dataset comprised 1,440 valid loading cycles (720 per condition). Cycle-level records were used for descriptive analysis and aggregated into 28 matched shift-level analysis blocks for inferential testing. Matching considered excavator–truck configuration, operator team and shift type, haul-distance category, material domain, production target, and trafficable weather and road conditions. Records with incomplete or non-chronological event timestamps or externally interrupted cycles were excluded without imputation. Average spotting time decreased from 30 s to 17 s (−43.3%), loading cycle time decreased from 167 s to 152 s (−9.0%), and excavator productivity increased from 859 BCM/h to 1,120 BCM/h (+30.4%). Paired tests on the 28 matched blocks produced df = 27 and confirmed significant improvements in spotting time and productivity (p < 0.001). The scientific contribution is field-based, statistically validated evidence linking a redesigned truck-approach sequence to both micro-cycle time and excavator productivity. DBL therefore offers a practical, low-capital operational option where mine geometry, traffic control, and safety conditions permit a continuous forward approach.