Analysis Of The Dominant Causes Of Time Delay In The Rehabilitation Project Of The Medical Outpatient Unit At Ratu Zalecha Regional General Hospital

Ahmad Muzakkiy (universitas islam kalimantan Muhammad Arsyad Al Banjari)
Ruliana Febrianty (Civil Engineering Study Program, Faculty of Engineering, Universitas Islam Kalimantan Muhammad Arsyad Al Banjari, Banjarmasin, South Kalimantan, Indonesia)
Robiatul Adawiyah (Civil Engineering Study Program, Faculty of Engineering, Universitas Islam Kalimantan Muhammad Arsyad Al Banjari, Banjarmasin, South Kalimantan, Indonesia)



Article Info

Publish Date
29 Oct 2026

Abstract

The rehabilitation project of the Medical Outpatient Unit at Ratu Zalecha Regional General Hospital (RSUD Ratu Zalecha) in Martapura was identified as experiencing schedule delays by Week 11, particularly in sanitary, mechanical, electrical, public address, and plumbing works. This study aims to evaluate the project's schedule performance using the Earned Value Management (EVM) method and to analyze and rank the dominant delay-causing activities based on the Schedule Performance Index (SPI). A quantitative approach was employed using secondary data, including weekly progress reports, the planned S-curve, and the project cost budget (Rencana Anggaran Biaya/RAB). The analysis revealed that the project's schedule performance fluctuated throughout the construction period, with the highest SPI of 2.47 recorded in Week 2 and the lowest critical SPI of 0.666 in Week 11, accompanied by a Schedule Variance (SV) of −IDR 342,921,182. Following acceleration measures implemented during Weeks 12 and 13, the project was completed on schedule with a final SPI of 1.00 and an actual expenditure of IDR 624,961,000 from the total budget of IDR 1,120,000,000. The ranking analysis of 16 work groups identified 11 groups with SPI values below 1.00 as the dominant contributors to project delays. The sanitary work group was the most critical (SPI = 0.235), followed by flooring (SPI = 0.311), painting (SPI = 0.356), and the public address system (SPI = 0.465). The two large weight groups, namely Sanitary and Flooring, are the most influential factors in the decline in project schedule performance in aggregate.

Copyrights © 2026






Journal Info

Abbrev

CES

Publisher

Subject

Civil Engineering, Building, Construction & Architecture

Description

Jurnal Civil Engineering Study (JCES) contains writings about applications in the field of Civil Engineering. This application may come from all branches of civil engineering, be it structural, geotechnical, construction management, hydrology, transportation, and civil engineering informatics. So ...