The success of a construction project is greatly influenced by optimal resource management, including human resources, materials, tools, and equipment. This study began with the problem of work delays that occurred in the surface facility construction project by contractors at PT X in the Rokan work area, especially in September, October, and November 2024. Based on observations, these delays occurred due to sub optimal resource management. This study aims to identify the factors causing delays and the existing resource management system, as well as to develop a simple mathematical model to support optimal resource allocation. The results obtained indicate that structured resource requirement modeling can significantly increase efficiency in terms of completion duration. The lowest value is 27 days vs. 21 days or 27% faster than manual calculation completion, the average value is 60 days vs. 21 days or 65% faster than manual calculations, and the highest is 96 days vs. 21 days or 79% faster than the previous plan.