Topsoil Management Strategy Based on Five-Year Sequence Scheduling to Support Reclamation Sustainability PT Ganda Alam Makmur

Athuur Mukti Muhakka (Fakultas Teknik, Universitas Sriwijaya)
Restu Juniah (Fakultas Teknik, Universitas Sriwijaya)
M. Taufik Toha (Fakultas Teknik, Universitas Sriwijaya)



Article Info

Publish Date
21 Oct 2026

Abstract

Open-pit coal mining operations require effective land reclamation, in which topsoil management plays a critical role in restoring soil productivity and supporting long-term environmental sustainability. However, mismatches between topsoil recovery schedules and the availability of reclamation areas can result in excessive stockpiling, repeated material handling, longer hauling distances, and increased operational costs. At PT GANDA ALAM MAKMUR, topsoil management had not been fully integrated with the mine production sequence, potentially reducing reclamation efficiency. This study aimed to evaluate existing topsoil management practices, develop an integrated management strategy based on a five-year mine sequence, and compare the operational and economic performance of the proposed strategy with existing conditions. An applied quantitative research approach using simulation-based modeling was employed, with the mine sequence treated as a fixed planning baseline. Spry mine planning software was used as a decision-support tool to evaluate spatial, temporal, operational, and economic aspects of topsoil management. Data were collected through field observations, document reviews, interviews, and a literature review. The findings indicated that only 2.291 million bank cubic meters (BCM), equivalent to 11.81% of the total estimated topsoil requirement of 19.393 million BCM, had been recovered under existing conditions, while the actual topsoil hauling distance exceeded 3 km. The proposed strategy integrated topsoil placement in designated storage areas (banksoiling), direct spreading, and rehandling activities with the planned progression of pit development and final landform preparation. Simulation results indicated that approximately 9.49 million BCM of topsoil could be managed, representing 48.94% of the estimated requirement, with an average annual management rate of 1.916 million BCM and a projected cumulative reclamation area of 1,025.83 hectares. The modeled weighted-average topsoil hauling distance ranged from 0.98 to 1.97 km, representing a reduction of approximately 34.33%–67.33% relative to a 3 km reference distance and generating estimated potential cost savings of USD 5.82 million. The study concluded that integrating topsoil management with the five-year mine sequence could improve material handling efficiency, reduce hauling requirements, and support more systematic reclamation planning. The proposed strategy emphasized the use of designated topsoil storage areas as operational buffers, complemented by field validation and periodic adjustments to accommodate actual mining and reclamation conditions

Copyrights © 2026






Journal Info

Abbrev

jr

Publisher

Subject

Humanities Economics, Econometrics & Finance Engineering Health Professions Social Sciences

Description

Enrichment: Journal of Multidisciplinary Research and Development is a double-blind, peer-reviewed journal covering multidisciplinary issues. Monthly published by International Journal Labs, the journal serves as a means of relevant discussion that fall within its focus and scopes. This journal ...