This study aims to analyze the operator workload in the Monza series leg production process in the TAKT 4 Production Unit 1 of PT Wahana Lentera Raya using the Workload Analysis (WLA) method. The process stages analyzed include lamination, trimming, touch up, and sealer. Data were collected through direct observation, interviews, and internship participation. The results of the study show the cycle time of each process: lamination 75 seconds, trimming 36 seconds, and touch up & sealer 37 seconds. With a rating factor of 1.25 and an allowance of 10%, the standard time obtained was 103.125 seconds (lamination), 49.5 seconds (trimming), and 50.875 seconds (touch up & sealer). The WLA values of each process were 1.26; 1.21; and 1.24, all of which are in the inload category. This means that the operator workload is balanced and work time has been utilized optimally. Keyword : Workload Analysis, workload, standard time, work efficiency, manufacturing industry.