Evaluation of Crane Capacity Utilization Based on Lifting Plan in Steel Silo Assembly and Erection Works: Evaluasi Pemanfaatan Kapasitas Crane Berdasarkan Lifting Plan Pada Pekerjaan Assembly Dan Erection Silo Baja

Windi Hidayanti (Program Studi Teknik Sipil, Fakultas Sains dan Teknologi, Universitas Muhammadiyah Sidoarjo)
Muhammad Alvan Rizki (Program Studi Teknik Sipil, Fakultas Sains dan Teknologi, Universitas Muhammadiyah Sidoarjo)



Article Info

Publish Date
18 Nov 2026

Abstract

General Background: Steel silo assembly and erection works involve the lifting of large and heavy components, which pose a high level of safety risk; therefore, crane capacity utilization becomes a critical aspect of construction planning. Specific Background: In field practice, crane selection is often based solely on nominal capacity without comprehensive consideration of operational factors, making a structured lifting plan essential. Knowledge Gap: Although previous studies discuss general lifting methods, comprehensive evaluations of crane capacity utilization based on actual lifting plan documents for steel silo structures remain limited. Aims: This study aims to evaluate crane capacity utilization based on lifting plan documents for steel silo assembly and erection works. Results: The evaluation indicates that during the assembly stage, the utilization of a 25-ton crane ranges from 11% to 58%, whereas during the erection stage, the utilization of a 50-ton crane ranges from 75% to 76%, remaining within acceptable safety limits. Novelty: This work introduces an empirical assessment linking lifted loads, working radii, boom lengths, and Safe Working Load (SWL) percentages across distinct assembly and erection phases. Implications: Utilizing lifting plan evaluations ensures operational safety while supporting work efficiency as a reference for heavy lifting operations in similar steel structure projects. Key Findings Highlights Crane utilization during the assembly stage ranges between 11% and 58%, providing a sufficient safety margin. During the erection stage, crane utilization reaches 75% to 76%, approaching operational limits while remaining within safe boundaries. Evaluating crane capacity based on lifting plans successfully balances operational safety and workflow efficiency in heavy component installation. Keywords Crane capacity utilization, Lifting plan, Assembly, Erection, Steel silo, Safe working load

Copyrights © 2026






Journal Info

Abbrev

PELS

Publisher

Subject

Computer Science & IT Control & Systems Engineering Electrical & Electronics Engineering Engineering

Description

PELS (Procedia of Engineering and Life Science) is an international journal published by Faculty of Science and Technology Universitas Muhammadiyah Sidoarjo. The research article submitted to this online journal will be double blind peer-reviewed (Both reviewer and author remain anonymous to each ...