unplanned material procurement in construction projects leads to cost overruns and work delays. This study aims to desig a material control model using the Material Requirement Planning (MRP) method and to determine the most efficient lot sizing technique for Engineering Laboratory And Workshop Building In Manado. The study employed a requirements, netting, lot sizing, and offsetting with a two-week lead time. The material examined was reinforcing steel, with an ordering cost of IDR 750,000 per order and a holding cost calculated from the cost of capital and depreciation. The results show that the net requirement for reinforcing steel from period 4 to period 12 was 105,996 kg. The Lot For Lot (LFL) technique resulted in a total cost of IDR 2,223,006.34, making LUC the most efficient technique, Therefore, MRP can serve as a basis for material procurement planning, and the selection of a lot sizing technique should consider the material cost burden.