Optimalisasi Waktu Pengerjaan Proyek Ruko Dengan Metode Diagram Preseden

Nilwan Andiraja (Jurusan Matematika, Fakultas Sains dan Teknologi, UIN Sultan Syarif Kasim Riau)
Rian Rian (Jurusan Matematika, Fakultas Sains dan Teknologi, UIN Sultan Syarif Kasim Riau)



Article Info

Publish Date
11 Nov 2015

Abstract

This research describes the optimization of the overall project timeline store using diagrams precedent method, the case study is project of store in PT. Odrimari Riau Pratam . The objective of this optimization is to accelerate the development of the project and predict the duration project to the structure 1. By determining the constraints and inside there are overlapping activities. Constraints contained in this diagram precedent method is constrained finish to start (FS), constraints begin to start (SS), constraints finished to finished (FF) and constraints start to finish (SF). Then, analysis with forward calculation and backward calculation and determine critical path. Base on analysis, the project of store is finish to the first structure in the prediction will be completed within 130 days when using precedent diagrams methood with the critical path for the project is . In this project there are non-critical activity is B, M and P not fulfilling condition to be a critical activity.Keywords: Constrain, Critical, Optimization, Precedent,Ttime

Copyrights © 2015






Journal Info

Abbrev

SNTIKI

Publisher

Subject

Computer Science & IT Control & Systems Engineering Electrical & Electronics Engineering Industrial & Manufacturing Engineering Mathematics

Description

SNTIKI adalah Seminar Nasional Teknologi Informasi, Komunikasi dan Industri yang diselenggarakan setiap tahun oleh Fakultas Sains dan Teknologi Universitas Islam Negeri Sultan Syarif Kasim Riau. ISSN 2579 7271 (Print) | ISSN 2579 5406 ...