SCHEDULING ANALYSIS USING THE PDM METHOD IN THE SYAMSUDIN NOOR AIRPORT ACCESS ROAD CONSTRUCTION PROJECT WITH THE HELP OF MICROSOFT PROJECT Witami, Nurisma; Khatimi, Husnul
CERUCUK Vol 10, No 3 (2026): CERUCUK VOL. 10 NO. 3 MARCH 2026
Publisher : Universitas Lambung Mangkurat

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.20527/crc.v10i3.18916

Abstract

Syamsudin Noor Airport Access Road Development Project, Landasan Ulin Sub-district, Banjarbaru City, South Kalimantan is a provincial road project carried out by the PUPR Office of South Kalimantan Province together with the Banjarmasin National Road Implementation Center. This project is carried out within 330 working days based on the schedule given in the form of Barchart. The implementation of this project should be completed in the shortest possible time, so that scheduling analysis is carried out using other methods, one of which is the Precedence Diagram Method (PDM). Through the results of the analysis in this study, it was found that the total duration of scheduling the Syamsudin Noor Airport Access Road Construction Project using the PDM method with the help of Microsoft Project was 221 working days and 270 calendar days, the total initial duration of the project was for 330 working days. The work started on September 25, 2023 and ended on 21 June, 2024. Keywords: Project, Scheduling, PDM, Project