This study aims to analyze the application of the exceptio non adimpleti contractus principle in breach of contract disputes arising from construction agreements, with particular reference to Supreme Court Decision No. 1796 K/Pdt/2015. This study employs a normative juridical research method using statutory, conceptual, and case approaches. The legal materials consist of primary legal materials, including the Civil Code and Supreme Court Decision No. 1796 K/Pdt/2015, as well as secondary legal materials obtained from legal books, scholarly journals, and relevant legal literature. The results indicate that the exceptio non adimpleti contractus principle is relevant to reciprocal construction agreements because the obligations of the main contractor and subcontractor are interdependent. A party may invoke this principle to refuse or postpone the performance of its reciprocal obligation when the counterparty has failed to perform its contractual obligations, provided that such non-performance can be legally established. The case demonstrates that disputes over payment cannot be assessed solely on the basis of the claimed physical progress of construction work but must also consider compliance with contractual specifications, completion requirements, handover procedures, and other agreed contractual obligations. The study further finds that the legal protection of subcontractors remains closely dependent on the contractual relationship with the main contractor and the ability to prove fulfillment of contractual performance. Therefore, clear contractual provisions concerning performance standards, payment mechanisms, handover procedures, default notices, and dispute resolution are essential to ensure legal certainty and balance between the parties in construction agreements.