The construction of the Jakarta Light Rail Transit (LRT) Phase 1B Velodrome–Manggarai line crosses a corridor with very high traffic density, so the elevated girder had to be built without disturbing the road beneath it. The prestressed concrete box girder superstructure was therefore erected segment by segment using the Balanced Cantilever Method (BCM), assisted by a Form Traveller frame that removes the need for ground-supported scaffolding. This study analyzes the implementation method of box girder concreting with a Form Traveller on the Velodrome–Manggarai Zone 1 package, specifically at pier P48B segment 1, using a descriptive case-study approach that combines direct field observation, documentation, interviews with project personnel, and review of the contractor's method statements over a thirty-day internship period. The analysis covers the work sequence prior to concreting, the three-stage segmental pour of the bottom slab, web, and top slab, concrete curing, and post-tensioning of the tendons. Results show that the method was executed systematically according to the technical specifications, the Form Traveller safely carried wet-concrete loads of about 2,050 kN per segment, and stressing was performed only after the concrete reached 28 MPa with an elongation tolerance of ±7%. The study concludes that BCM combined with a Form Traveller is an effective solution for elevated rail infrastructure over active roads, provided that technical control and occupational safety are consistently maintained.