Haul road rehabilitation should be assessed through both the distribution of road support and the transport components that constrain productivity. This study examined an approximately 1 km section of Jalan Mukmin at Gurimbang Mine Operation, PT Berau Coal, Indonesia, following combined nonwoven geotextile placement, aggregate addition, and compaction. A descriptive before-and-after comparison used penetration-derived California bearing ratio (CBR) estimates at ten stations and reported Komatsu HD785 speeds and cycle-time components. Station dispersion, a diagnostic exclusion of the highest post-rehabilitation estimate, and cycle-time sensitivity were evaluated. Mean CBR increased from 21.58% to 60.01%, while its coefficient of variation increased from 19.33% to 57.97%. Nine stations improved, but one decreased. Excluding the highest station for sensitivity analysis retained a mean increase from 21.92% to 51.78%, indicating that the direction of change was not dependent on that station alone. Cycle time decreased from 22.06 to 16.62 min; loaded travel accounted for 65.63% of the reduction. Under fixed volume and efficiency assumptions, calculated productivity increased from 115.46 to 153.25 bank cubic metres per hour. An illustrative additional 1 min of cycle delay reduced the post-rehabilitation estimate to 144.56. The contribution is a transparent joint assessment showing why a higher mean road-support estimate does not establish spatial uniformity, and why operational gains depend on preserving travel-time savings. Uncontrolled conditions and discrepancies between penetration logs and summary values limit causal attribution and the geotechnical magnitudes. The results support targeted station verification and component-based transport monitoring, rather than certification of long-term road stability or an isolated geotextile effect.