Abstract: This study was done to control the delivery system components of Plant 1 to Plant 2 for the machine assembly is not off. The main problem faced by PT. FSCM Manufacturing Indonesia is not their delivery schedules so that components are submitted can not be controlled. The next problem is the production Planning is administered orally and the misscomunication between foremen and operators that cause components to ASF (After Surface Finishing) empty. Improvement award is to create the delivery schedule number and weight of components with components that have been determined. Make a design planning card to make the order type of components to be processed so that the planning of production to be sustainable and ASF components will not be empty. To draft a new component card for improving the quality of the product components