Pengembangan Metode Percepatan Penjadwalan Pada Keterlambatan Proyek EPC Di Fase Pelaksanaan Dengan Analisa “What If” Pratiwi Setyaning Putri; Hastanto S. M Hastanto S. M
FORUM MEKANIKA Vol 8 No 2 (2019): JURNAL FORUM MEKANIKA
Publisher : Sekolah Tinggi Teknik - PLN

Show Abstract | Download Original | Original Source | Check in Google Scholar | Full PDF (279.471 KB) | DOI: 10.33322/forummekanika.v8i2.537

Abstract

This study aims to analyze corrective actions that can be done if there is a project delay in one of the activities. Data collection techniques are carried out by observation. The gap between the actual and planned scheduling level (productivity gap) is a problem that must be evaluated and the root cause that causes the decline in work productivity is sought. After further evaluation, it is planned to re-target the acceleration that will be achieved both in the short and long term. The acceleration method for scheduling the duration of the project is done by the critical path method or CPM (Critical Path Method) for further development of corrective actions that can be done to overcome the delay in the duration of the project.
Pelatihan Pelaksanaan K3 Terhadap Risiko Kebakaran Di Madrasah Ibtidaiyah Al Huda Pratiwi Setyaning Putri
Terang Vol 3 No 1 (2020): TERANG : Jurnal Pengabdian Pada Masyarakat Menerangi Negeri
Publisher : Sekolah Tinggi Teknik - PLN

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.33322/terang.v3i1.1013

Abstract

Indonesia is the most vulnerable country to disasters in the world based on data released by the United Nations Agency for the International Strategy for Disaster Risk Reduction (UN-ISDR) [1]. This will certainly have an impact on the number of fatalities if there is no understanding and good handling of the parties involved. Alert and alert attitudes are still very minimal and are often not taught in formal teaching and learning activities. In addition to human resources, disaster risk reduction can also be pursued by providing adequate K3 facilities in each building. Madrasah Ibtidaiyah Al Huda which is on Jalan Al Huda Rawasapi RT 02/09 Kelurahan Jatimulya - Tambun Selatan Bekasi District has a moderate earthquake risk. In addition, the location of schools that are not on the main road and access roads to locations that are relatively difficult to pass by fire trucks make it vulnerable in the event of a fire disaster. The solution offered is education of OHS implementation of disasters and the provision of facilities and infrastructure to deal with these disasters. The expected output targets are one PKM article published through an ISSN journal, one ISBN proceeding article from a national seminar organized by STT-PLN, and publication in print / electronic media.