ANALISIS UMUR PROYEK DENGAN METODE PROGRAM EVALUATION AND REVIEW TECHNIQUE (PERT) PADA PROYEK RENOVASI BANGUNAN MES DAN SARANA PENDUKUNG KANTOR BALAI PENGKAJIAN TEKNOLOGI PERTANIAN BALI I Gede Ngurah Sunatha; Tjokorda Istri Praganingrum; Yohana Jusna
Jurnal Ilmiah Kurva Teknik Vol. 10 No. 1 (2021): Jurnal Ilmiah Kurva Teknik
Publisher : Program Studi Teknik Sipil Fakultas Teknik Universitas Mahasaraswati Denpasar

Show Abstract | Download Original | Original Source | Check in Google Scholar | Full PDF (240.352 KB) | DOI: 10.36733/jikt.v10i1.2139

Abstract

Office buildings listed into universal facilities buildings are one type of construction projects thatrequire a good project management to design, organize, perform and organize the construction project itself. Toachieve the success of the project needs to create a planning agenda that matches the wishes to be achieved. Ingeneral, project scheduling makes use of waku estimates of course. But the reality in the field of various obstaclesoccurred during the implementation of the project. therefore, researchers are trying to rescheduling theimplementation time of the Mess Building Renovation Project as well as supporting facilities of the BaliAgricultural Technology Assessment Office to recognize the maximum time of completion of the project. ProjectEvaluation and Review Technique (PERT) is one of the management tools in ensuring the scheduling of a projectby estimating the level of success. The pert procedure estimates 3 times is optimistic time, pessimistic time andvery maximum time. The level of accuracy estimated at the time of completion of the project is determined by thelevel of accuracy estimated the duration of each activity in the project. In analyzing calculations with the PERTmethod, an application-shaped tool, Microsoft Project, is used to manage projects. This application generallymakes it easier for users to create a work plan so that the implementation of the project can take place accordingto the agenda, mastering the influence of possible changes that occur, which can have an effect in the process ofproject implementation, financial scheduling and to unite businesses through communication and reporting ofproject data. Based on the results of the research that has been done, obtained optimistic project plan age of 128working days, the expected project plan age of 140 working days, the age of the pessimistic project plan of 153working days, and the optimum plan age (Te) of 141 working days.
EVALUASI DURASI PROYEK DENGAN METODE PROBABILITAS PADA PROYEK RENOVASI BANGUNAN MES DAN SARANA PENDUKUNG KANTOR BALAI PENGKAJIAN TEKNOLOGI PERTANIAN BALI Yohana Jusna; I Gede Ngurah Sunatha; Tjokorda Istri Praganingrum
Jurnal Ilmiah Teknik Universitas Mahasaraswati Denpasar (JITUMAS) Vol. 1 No. 1 (2021): Jurnal Ilmiah Teknik UNMAS Denpasar
Publisher : Fakultas Teknik Universitas Mahasaraswati Denpasar

Show Abstract | Download Original | Original Source | Check in Google Scholar

Abstract

In order for office buildings to always be functional, building maintenance and maintenance activities need to be done both physical maintenance and facilities and infrastructure that support office activities. The process of maintaining and upgrading buildings is inseparable from the role of good project management in planning, implementing and controlling the project itself. in the implementation of the project time and cost greatly affects the success rate of the project. In the mess building renovation project and supporting facilities office of the Bali Agricultural Technology Assessment Center the implementation time is not in accordance with the scheduling made. Therefore, the analysis of the review time of the implementation of the project is important again. in this study the authors used a method of probabilities analysis to determine the age of the project optimistic duration, expected duration and pessimistic duration. with a project success rate of 85% and a failure rate of 15%. Basically, probability theory intends to examine and measure uncertainty (uncertainly) and try to explain quantitatively. Based on the results of the analysis that has been done obtained the results of the duration of optimist, expected and pessimistic of each item with a probability rate of 85% success rate and 15% failure rate of the project on each work item has a duration of 1-3 days from normal time.