ANALISIS PERANCANGAN USAHA PRODUK PEMILAH SAMPAH ORGANIK DAN ANORGANIK MODERN putra, festo renza ardhana
JUSTI (Jurnal Sistem dan Teknik Industri) Vol 4 No 2 (2023): justi
Publisher : Universitas Muhammadiyah Gresik

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.30587/justicb.v4i2.7170

Abstract

In designing product design, the purpose of making modern waste bins for organic and non-organic sorting is to overcome waste management problems in Indonesia. By looking at these problems, we strive to create innovations so that people can understand a good way to manage waste. The product to be developed is a trash can with an automatic sorting sensor system, allowing the selection of waste one by one. by using the Economic Order Quantity method aims to assist companies in overcoming the problem of controlling raw material inventory Economic Order Quantity. Research shows that the manufacture of modern trash cans involves several steps, such as attention to product images, quality, size, and durability. Another strategy involves determining prices after market research to find prices that match consumer needs and wants. From these calculations, the production of modern trash cans can be considered feasible and beneficial to society, can help reduce littering and minimize piles of garbage. This modern waste separator product is expected to provide great benefits to the community and become a valuable learning.
Project Delay Factor Analysis Using Fault Tree Analysis (FTA) Method and Rescheduling with Critical Path Method (CPM) in Ducting Manufacturing Projects at PT. FRA Putra, Festo Renza Ardhana; Widyaningrum, Dzakiyah
Advance Sustainable Science, Engineering and Technology Vol 6, No 2 (2024): February - April
Publisher : Universitas PGRI Semarang

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.26877/asset.v6i2.18636

Abstract

Ducting manufacturing project at PT. The FRA was planned to be completed in 14 days, but was implemented in 19 days and 5 days late. The method to find the cause of project delays is Fault Tree Analysis (FTA), then analyze rescheduling with the Critical Path Method (CPM). The purpose of this study is to identify factors of work delay, determine new steps for project contractors and reschedule with alternative working hours and labor additions. The results of the analysis using the FTA method obtained the main cause of delay in drawing engineering work of 0.0002592 and obtained 4 new steps for project contractors. The results of rescheduling using the CPM method obtained a percentage increase in productivity with the alternative of adding working for 4 hours with a duration of 25% or 6 days faster than the normal duration of 19 days to 13 days and an additional cost of 91.96%, which is Rp. 21,500,000. While the percentage of productivity increase with alternative labor additions with a duration of 38.75% or 5 days faster than the normal duration of 19 days to 14 days and additional costs of 178.57%, namely Rp. 31,200,000. So it can be concluded by using the FTA method the main cause is drawing engineering work and 4 new steps are obtained and using the CPM method alternative scheduling is obtained to increase overtime work hours more effectively and additional costs are not too large, so that the company does not experience delays for future ducting projects.