ANALYSIS OF THE INFLUENCE OF ORDER VARIATION FACTORS ON THE COSTS AND TIME OF IMPLEMENTING CHANNEL DIVERCTION INFRASTRUCTURE CONSTRUCTION PROJECTS IN RESIDENTIAL AREAS Hindami, Ghazi Ghossan; Suroso, Agus; Amin, Mawardi
Jurnal Pensil : Pendidikan Teknik Sipil Vol. 13 No. 2 (2024): Jurnal Pensil : Pendidikan Teknik Sipil
Publisher : LPPM Universitas Negeri Jakarta

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.21009/jpensil.v13i2.43872

Abstract

Tangerang is a big city in Indonesia. The housing sector rocketing in this region. Changes in development often occur because problems arise and have an impact on costs and time. Researchers focused on finding the cause of the work diverting residential channels being hampered. For this reason, changes were made to the sheetpile design and changes to the infrastructure mobilization method to meet the contract time. The research uses the SEM PLS method to determine the factors causing order variations. In addition, the data processing application was used to determine the effect of order variations on time and cost performance. The respondents were 60 owners and consultants. Based on the results of the cost performance analysis, additional work arising from order variations reached 10,516,305,346 IDR and reduced work due to order variations reached 6,628,461,533 IDR or around 12.96% of the initial contract price and the results of time performance analysis for time losses that occurred due to order variations on the project showed an additional time of 5 months or 125%.
Analysis of the Influence of Order Variation Factors on the Costs and Time of Implementing Channel Diversion Infrastructure Construction Projects in Residential Areas Hindami, Ghazi Ghossan; Suroso, Agus; Amin, Mawardi
ASTONJADRO Vol. 13 No. 3 (2024): ASTONJADRO
Publisher : Universitas Ibn Khaldun Bogor

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.32832/astonjadro.v13i3.16249

Abstract

Tangerang is one of the big cities that is developing in Indonesia. Along with the development of the city, one sector that is increasingly developing is the housing sector. In implementing construction projects, problems are often faced, one of which is the occurrence of changes. Almost all existing projects experience variation orders (VO). Variation orders always have cost and time implications. Whatever the variation, there will be risks to the work being done, both in terms of work delays and additional costs that must be borne. Research using the SEM PLS method was carried out to find out what factors cause variation orders and how they affect time and cost performance in channel diversion infrastructure projects in residential areas. Based on the results of responses from correspondents, the significant value that influences project performance is planning and design with indicators of errors in planning drawings. Based on the results of the cost performance analysis for the amount of costs resulting from variation orders on work, the total increase was IDR. 10.516.305.346 and for less work the total is IDR. 6.628.461.533 around 12.96% of the initial contract price and the results of the time performance analysis for the amount of time resulting from variation orders on the project work show that there was a time extension of 5 months or 125%.