Kapabilitas Dinamik Pada Akselerasi Produksi Precast Girder Tipe- U pada Proyek LRT Jabodebek Hermawan, Ferry; Susanto, Tri; Purwanggono, Bambang; Setiadji, Bagus Hario; Pratiwi, Anik Nurul
MEDIA KOMUNIKASI TEKNIK SIPIL Volume 30, Nomor 1 (2024)
Publisher : Department of Civil Engineering, Diponegoro University

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.14710/mkts.v30i1.62443

Abstract

LRT Jabodebek sebagai proyek infrastruktur LRT pertama di Indonesia telah memberikan pembelajaran tentang implementasi kapabilitas dinamik pada aspek manufaktur bagi industri konstruksi. Dalam rangka memenuhi kebutuhan 2900 unit girder precast tipe-U, produksi dalam kondisi normal diharapkan selesai pada tahun 2020. Akselerasi penyelesaiannya menyebabkan kebutuhan proyek meningkat signifikan, penyelesaian konstruksi yang dipercepat menyebabkan kendala kekurangan produksi. Pemenuhan kebutuhan akselerasi tersebut menuntut pabrik harus dapat meningkatkan kapasitas produksinya dengan menggunakan metode steam curing. Studi kasus ini menggunakan pendekatan kualitatif dan berfokus pada kapabilitas dinamik dalam proses produksi. Sebagai role model penerapan kapabilitas dinamik manufaktur, proyek ini telah mendemonstrasikan peran teknologi dalam peningkatan produktivitas. Integrasi metode, posisi aset, dan proses manajemen adalah faktor produktivitas yang paling dominan dalam mempercepat produksi precast girder tipe-U. Performa produksi yang optimal dapat dicapai dengan mengintergrasikan peran pabrik, site proyek, dan manajemen yang didukung oleh sumber daya dan pengalaman personil yang memadai
Cost and Time Performance Evaluation of a Sports Hall Construction Project Using the Earned Value Method: A Case Study at Gunung Kidul Campus, Universitas Negeri Yogyakarta Pratiwi, Anik Nurul; Prihadi, Wisnu Rachmad; Al-Pashya, Muhammad Donny Reval
INERSIA lnformasi dan Ekspose Hasil Riset Teknik Sipil dan Arsitektur Vol. 21 No. 1 (2025): May
Publisher : Universitas Negeri Yogyakarta

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.21831/inersia.v21i1.84089

Abstract

The main objectives in managing construction work involve controlling costs, ensuring quality, and meeting project deadlines. Construction projects are regarded as successful when they deliver outputs that satisfy predefined quality standards, are finished on time, and stay within the agreed budget. The Earned Value Method (EVM) is a valuable technique in project management for assessing both cost efficiency and schedule adherence throughout the project’s duration. Important indicators for this analysis include BCWP (Budgeted Cost of Work Performed), BCWS (Budgeted Cost of Work Scheduled), ACWP (Actual Cost of Work Performed), Schedule Variance (SV), Cost Variance (CV), Schedule Performance Index (SPI), Cost Performance Index (CPI), Estimated At Schedule (EAS), and Estimated Temporary Schedule (ETS). This research focuses on evaluating the performance of the Sports Hall Building construction project at Gunung Kidul Campus by applying the earned value method. The assessment emphasizes time scheduling and cost management to gauge how well the project progresses relative to its planned schedule and budget. The study’s findings reveal the current condition of both cost and schedule aspects of the Sports Hall Building project at Gunungkidul Campus, Universitas Negeri Yogyakarta. The data showed a positive cost variance, indicating that the project’s actual expenditures were less than originally planned.