ANALISIS RAB STRUKTUR BETON GEDUNG RSUD YOGYAKARTA MEGGUNAKAN REVIT Sayifullah Bustomi Abiyasa; M. Afif Shulhan; Dimas Langga Chandra Galuh
RENOVASI : Rekayasa Dan Inovasi Teknik Sipil Vol 9 No 2 (2024): October
Publisher : Department of Civil Engineering, Faculty of Engineer, Universitas Sarjanawiyata Tamansiswa

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.30738/renovasi.v9i2.19291

Abstract

The analysis of the Bill of Quantities (BOQ) for the concrete structure of the RSUD Yogyakarta building is an analytical activity that uses Autodesk Revit Software. The issue that arises is estimating the costs and identifying which items are calculated using Revit. The solution to this problem using Autodesk Revit Software is by identifying the modeling and then extracting the volume of each work item, such as reinforcement and rebar, within Autodesk Revit. The calculation results using Autodesk Revit show the volume of each work item. For the foundation work, it requires 159.3 m³ for concrete pouring and 18,658.6 kg for rebar. For the first floor, concrete pouring requires 174.58 m³ and rebar weighs 29,307.6 kg. On the second floor, the concrete pouring volume is 182.06 m³ with rebar weighing 27,196.17 kg. The third floor requires 139.81 m³ of concrete and 21,810.75 kg of rebar. Finally, for the concrete roof deck, the rebar volume is 25.98 m³ with rebar weighing 1,572.99 kg. Thus, the total concrete pouring volume is 681.73 m³, and the rebar weight is 98,546.17 kg. From the volume, an estimation of the reinforcement and rebar costs for each work item is generated. The foundation work requires a cost of IDR 373,090,357.00 for concrete pouring and IDR 1,758,704,534.00 for rebar. For the first floor, the concrete pouring costs IDR 107,569,354.00, and the rebar costs IDR 962,141,433.00. On the second floor, the concrete pouring costs IDR 97,560,372.00, with rebar costing IDR 1,261,605,190.00. The third floor requires IDR 50,112,904.00 for concrete pouring and IDR 696,583,946.00 for rebar. Finally, for the concrete roof deck at a height of 12.45 m, the rebar costs IDR 49,215,359.00, with rebar totaling IDR 685,800,691.00. Thus, the total overall cost for the RSUD Yogyakarta building is IDR 9,065,085,905.00.
ANALISIS RAB STRUKTUR BETON GEDUNG TIGA LANTAI MENGGUNAKAN METODE AUTODESK REVIT DAN ANALITIS Yoga Zul Azam; Dimas Langga Chandra Galuh; M. Afif Shulhan
RENOVASI : Rekayasa Dan Inovasi Teknik Sipil Vol 9 No 2 (2024): October
Publisher : Department of Civil Engineering, Faculty of Engineer, Universitas Sarjanawiyata Tamansiswa

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.30738/renovasi.v9i2.19293

Abstract

Year by year, there has been a sharp increase in the development of roads, buildings, and other infrastructures focused on communities in various parts of the country. This growth has driven the construction sector to work more efficiently and integrated, especially with the advancement of technology and communication. Building Information Modeling (BIM), which allows for more efficient and integrated design and construction processes, is one of the new options. However, effective time and cost planning remain major challenges. Therefore, careful planning is essential to ensure the success of construction projects. BIM enables building modeling in three dimensions, which helps in better project visualization. One of the most commonly used BIM programs is Autodesk Revit, which combines various disciplines such as architecture, structure, and MEP (Mechanical, Electrical, Plumbing).