Time Analysis on the Kuningan Eastern Ring Road Prasetyo, Sigit Widiyatmo; Darmawan, Dicky; Firdaus, Dinda; Kusumastuti, Aryati Indah
Indonesian Journal of Advanced Research Vol. 4 No. 12 (2025): December 2025
Publisher : PT FORMOSA CENDEKIA GLOBAL

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.55927/ijar.v4i12.15876

Abstract

This analysis aims to identify delay factors and reduce the risk of delay in construction projects using the CPM method in the construction project of the East Ring Road Kuningan. The results of the study show that common factors that can have an impact on delays include the provision of materials, workforce readiness, and schedule adjustment to weather conditions. Therefore, supervision and control on critical routes must be carried out intensively to ensure that the project can be completed on time according to plan because delays in one activity alone will have a direct impact on the overall project completion.