Analisis Kelayakan Harga Tenaga Listrik PLTS dengan Metode Life Cycle Cost dan LCOE Vetty Kartikasari; Agus Yudi Asmoro; Aang Fajar Passa Putra; Digitha Oktaviani Putri; Ika Anggraeni Khusnul Khotimah
Journal of Industrial View Vol. 6 No. 1 (2024)
Publisher : Universitas Merdeka Malang

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.26905/jiv.v6i1.13093

Abstract

Abstract The plan to develop PLTS with a capacity of 50Mwp in Galang Batang SEZ is a form of commitment of the wilus holder to the mandate of Presidential Regulation 112 of 2022 in order to achieve the 23% EBT mix target in 2025. In accordance with the RUPTL document of the owner of the area in 2024-2033, which plans the development of power plants to be cooperated with IPP business entities. So that a techno-economic study is needed to provide an overview of project life cycle costs (LCC), electricity production costs, electricity selling prices and financial feasibility. From the results of the calculation, the Life Cycle Cost (LCC) value obtained in the present value of Rp. 587,672,449,561 and energy production during the project period in PV is 576,918 Mwh so that the resulting cost of electricity production calculated by the LCOE method is Rp. 1,018.64 / kwh or 6.37 cUsD. The scenario of the selling price of electricity with a 10% margin gives a positive NPV result of Rp. 34,590 billion; an IRR value of 10.58% above the WACC of 9.69% and a payback period of 8 years and 9 months. So that the development of PLTS in Galang Batang SEZ by IPP business entities is feasible to be realized.Abstrak Rencana pengembangan PLTS berkapasitas 50Mwp di KEK Galang Batang merupakan bentuk komitment pemegang wilus terhadap amanat perpres 112 tahun 2022 dalam rangka mencapai target bauran EBT 23% di tahun 2025. Sesuai dengan dokumen RUPTL pemilik wilus kawasan tahun 2024-2033 yang merencanakan pengembangan pembangkit untuk dikerjasamakan dengan badan usaha IPP. Sehingga  diperlukan suatu  kajian tekno ekonomi untuk memberikan gambaran terkait biaya siklus hidup proyek (LCC) , biaya produksi tenaga   listrik , harga jual tenaga listrik dan  kelayakan finansial nya. Dari hasil perhitungan, diperoleh nilai Life Cycle Cost (LCC)  yang di present value kan sebesar Rp 587.672.449.561 dan produksi energi selama periode proyek yang di PV kan sebesar 576.918  Mwh sehingga  yang menghasilkan  biaya produksi tenaga  listrik  yang dihitung dengan metode LCOE sebesar Rp. 1.018,64/kwh atau 6,37 cUsD. Skenario harga jual tenaga listrik dengan margin 10% memberikan hasil NPV positif   Rp. 34,590 Miliar; nilai  IRR 10,58%  diatas WACC 9,69% dan pengembalian /payback period 8 tahun 9 bulan. Sehingga pengembangan PLTS di KEK Galang Batang oleh badan usaha IPP layak untuk direalisasikan.
Manajemen Risiko Bisnis Kafe pada Bauran Pemasaran dengan House of Risk (HOR) Vetty Kartikasari; Maria Nirmala Odja; Ni Made Wiati
Journal of Industrial View Vol. 7 No. 1 (2025)
Publisher : Universitas Merdeka Malang

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.26905/jiv.v7i1.15702

Abstract

Cafe X in Malang City is facing business challenges that may threaten its sustainability. To enhance its competitiveness, the café has reviewed its marketing strategy by integrating the 7P-based marketing mix (Product, Price, Place, Promotion, Process, People, and Physical Evidence) with risk management using the House of Risk (HOR) approach. This study aims to formulate an adaptive, market-oriented marketing strategy while proactively identifying and mitigating potential risks associated with each element of the marketing mix. In the first phase of the HOR analysis, 10 risk events and 22 risk agents were identified, with 7 priority risk agents determined based on the highest Aggregate Risk Potential (ARP) values and visualized using a Pareto diagram. In the second phase, 8 preventive actions were prioritized according to their Effectiveness to Difficulty (ETD) ratio and degree of difficulty of implementation. Recommended mitigation actions include optimizing digital promotional media, implementing systematic promotional strategies, enhancing cost-efficiency, developing market-driven product innovations, and strengthening human resource capacity to adapt to evolving market needs and café industry trends.    Kafe X di kota Malang mengalami permasalahan dalam bisnis yang berpotensi menghambat kelangsungan usaha,  sehingga melakukan review implementasi startegi pemasarannya untuk  meningkatkan daya saing. Integrasi antara marketing mix berbasis 7P (Product, Price, Place, Promotion, Process, people dan Physical Evidence) dengan manjemen risiko menggunakan House of Risk menjadi salah satu solusi terpilih  bagi kafe X untuk menyelesaikan persoalan yang ada. Dengan menyusun strategi pemasaran yang adaptif dan berbasis kebutuhan pasar serta  secara proaktif mengidentifikasi dan mengelola berbagai risiko potensial dari tiap elemen bauran pemasaran.  Hasil penelitian ini menyebutkan pada fase HOR 1 teridentifikasi 10 risk event dan 22 risk agent serta 7 agen risiko prioritas dengan nilai Aggregate Risk Potential (ARP) tertinggi yang dimaping dengan diagram pareto. Pada fase HOR 2 dihasilkan 8 preventive action yang diprioritaskan sesuai dengan effectiveness to difficulty / ETD dan  tingkat kesulitan implementasi. Aksi mitigasi tersebut meliputi optimalisasi penggunaan media promosi digital, perancangan dan pelaksanaan strategi promosi yang sistematis, strategi efisiensi  biaya, inovasi produk berbasis pasar  serta penguatan kapasitas sumber daya manusia agar lebih adaptif terhadap kebutuhan pasar dan tren industri  kafe saat ini