Kajian Percepatan Proyek dengan Metode Time Cost Trade Off pada Proyek Pembangunan Jalan Tol Balikpapan-Samarinda Seksi V: Acceleration of Project Using the Time Cost Trade off Method Assessment in Balikpapan-Samarinda Toll Road Development Project, Section V

Rida Respati (Universitas Muhammadiyah Palangka Raya)
Agus Sugianto (Universitas Balikpapan)
Wisnu Bagus Santoso (Universitas Balikpapan)



Article Info

Publish Date
21 Jun 2021

Abstract

Proyek adalah sebuah kegiatan yang bersifat sementara yang telah ditetapkan awal pekerjaannya dan waktu selesainya. Proyek pembangunan Ruas Jalan Tol Balikpapan-Samarinda Seksi V dimulai dari KM 13-Manggar dengan panjang 10,9 km ini dipilih sebagai objek penelitian. Metode yang dapat digunakan untuk mempercepat durasi proyek adalah metode time cost trade off. Tujuan dari penelitian ini adalah mengetahui perbandingan antara biaya dan waktu sebelum dan sesudah penerapan time cost trade off dan mengetahui besar biaya dan waktu optimum menggunakan metode time cost trade off. Hasil penelitian menunjukkan bahwa setelah dilakukan percepatan menggunakan alternatif penambahan jam kerja lembur, diperoleh biaya optimum sebesar Rp853.423.789.864,55 dan waktu optimum 414 hari dengan efisiensi biaya proyek 0,47% dan efisiensi waktu proyek 55,48%, Sedangkan percepatan menggunakan alternatif penambahan jumlah alat berat, diperoleh biaya optimum sebesar Rp858.865.629.963,50 dan waktu optimum 496 hari dengan efisiensi biaya proyek 0,17% dan efisiensi waktu proyek 46,67%. A project is a temporary activity that has been set early work and completion time. Toll road construction project Balikpapan-Samarinda Section V starts from KM 13-manggar with a length of 10.9 km was selected as the research object. The method can be used to speed up the duration of the project is the method of time cost trade off. The purpose of this study was to determine the ratio between the cost and the time before and after the implementation time cost trade off and find out the cost and time of optimum uses time cost trade off. The results showed that after the addition of acceleration using the alternate hours of overtime work, obtained the optimum cost Rp853.423.789.864,55 and optimum time of 414 days with 0.47% project cost efficiency and time efficiency of 55.48% project, While the acceleration using the alternate addition of heavy equipment, obtained the optimum cost Rp858.865.629.963,50 and optimum time of 496 days with 0.17% project cost efficiency and time efficiency of 46.67% project.

Copyrights © 2021






Journal Info

Abbrev

transukma

Publisher

Subject

Civil Engineering, Building, Construction & Architecture

Description

Jurnal Transukma merupakan jurnal ilmiah teknik sipil sebagai media publikasi ilmiah untuk hasil-hasil inovasi terkini dalam bidang teknik sipil. Media publikasi ini sebagai wadah untuk menuangkan gagasan dan ide dalam pengembangan keilmuan ataupun permasalahan yang ada di dalam masyarakat untuk ...