GANEC SWARA
Vol 17, No 2 (2023): Juni 2023

ANALISIS PERCEPATAN WAKTU PELAKSANAAN PROYEK DENGAN PENAMBAHAN JAM KERJA (STUDI KASUS PEMBANGUNAN LAHAN PARKIR RUMAH SAKIT BANGLI MEDIKA CANTI)

I PUTU YANA HERMAWAN (Program Studi Teknik Sipil Fakultas Teknik Unversitas Mahasaraswati Denpasar)
I GEDE NGURAH SUNATHA (Program Studi Teknik Sipil Fakultas Teknik Unversitas Mahasaraswati Denpasar)
ANAK AGUNG RATU RITAKA WANGSA (Program Studi Teknik Sipil Fakultas Teknik Unversitas Mahasaraswati Denpasar)
KADEK ANDY SADEWA (Program Studi Teknik Sipil Fakultas Teknik Unversitas Mahasaraswati Denpasar)



Article Info

Publish Date
01 Jun 2023

Abstract

Implementation of a construction project has a series of activities or jobs that are complex and interdependent on one another. Construction project development is carried out in several stages of work, one of which is making a work schedule. Work schedules are made to make it easier for each activity to be carried out sequentially and on time. In the implementation of the Parking Lot Construction Project at Bangli Medika Canti Hospital, there was a delay in weekly progress. To anticipate changes in implementation time, an acceleration of implementation time is carried out using the method of adding overtime hours. In this research, acceleration of implementation time was carried out using the method of adding overtime hours based on Microsoft Project. The data used in this study are in the form of a planned time schedule, realization time schedule, and weekly reports. The analysis was carried out to obtain the results of activities that can be accelerated and the project implementation time after being accelerated using the method of adding overtime hours. From the results of the analysis of the Microsoft Project, there are activities that can be accelerated, namely as many as 23 work items. After analyzing with the method of adding overtime hours on the implementation of the Parking Lot Development Project at Bangli Medika Canti Hospital, the project time was 122 days. This time is the same time at the initial planning. In the process of implementing the project, there was a delay in progress which resulted in a postponement of the project plan schedule to 129 days.

Copyrights © 2023






Journal Info

Abbrev

GARA

Publisher

Subject

Agriculture, Biological Sciences & Forestry Education Engineering Law, Crime, Criminology & Criminal Justice Social Sciences

Description

Ganec Swara merupakan wadah untuk hasil penelitian dan ulasan ilmiah pada bidang-bidang ilmu seperti Ilmu Sosial, Pertanian, Ekonomi, Teknik, Hukum, Kependidikan dan ...