Setrum : Sistem Kendali-Tenaga-elektronika-telekomunikasi-komputer
Vol 12, No 2 (2023): Edisi Desember 2023

Analisa Alarm pada Device Proteksi Generator dan Transformer PLTU Jawa 7 Terhadap Grounding Fault yang Terjadi di SUTET Outline LBE Line I 500kV

Ahmad Ilham Kamal (PT. GHPJB, O&M PLTU JAWA 7)
Nur Rahma Dona (Guohua Taidian Pembangkitan Jawa Bali Co., Ltd, O&M USC JAVA 7 CFPP)



Article Info

Publish Date
05 Dec 2023

Abstract

In every PLN 500kV grid system power plant in Jamali (Java-Madura-Bali) it is connected in parallel between the generators with a substation as a connector. The function of the substation itself is to equalize the voltage between generators. The case in this journal is the 500kV grid and also functions as a breaker area when a disturbance (short circuit) occurs at a certain point, which will make the 500kV system remain reliable so that it can always distribute electricity to consumers. Analysis of alarms in the generator protection system when a disturbance occurs on the outside of the power plant functions to ensure that the protection equipment in the unit is functioning normally or not, and functions to ensure that the fault location point is not in the internal electrical system of the power plant, and also functions to ensure that the outline protection relay is working. normally according to calculations and design.

Copyrights © 2023






Journal Info

Abbrev

jis

Publisher

Subject

Education

Description

SETRUM : Sistem Kendali Tenaga Elektronika Telekomunikasi Komputer merupakan jurnal yang diterbitkan oleh Jurusan Teknik Elektro, Fakultas Teknik, Universitas Sultan Ageng Tirtayasa (UNTIRTA) sejak 2012 menggunakan sistem Open Journal System ...