APLIKASI VALUE ENGINEERING PADA PEKERJAAN TAMBAH KURANG UNTUK MENINGKATKAN EFISIENSI BIAYA KONTRAKTOR (Studi Kasus: Gedung D BPOM Jakarta)

Hidayat, Indra (Unknown)
Wibowo, Kartono (Unknown)
Sumirin, Sumirin (Unknown)



Article Info

Publish Date
01 Dec 2024

Abstract

Cost planning is one of the important things in a development project, both for theproject owner and the implementing contractor. The contractor has a planned costtarget at the tender stage, however, changes in costs may occur during theimplementation period due to additional or less work and resulting in changes incosts. To be able to achieve the cost efficiency target, this can be done by carryingout value engineering. The stages of the value engineering method consist of theinformation stage, function analysis stage, creativity stage, evaluation stage,development stage and recommendation stage. The application of value engineeringin the BPOM Building D Construction Project can provide an increase cost and stillmaintain function. Contractor get cost efficiency of IDR 1,528,657,929,- or 2.52%,while the project owner gets a cost efficiency of IDR 1,182,279,319 or 1.66%.

Copyrights © 2024






Journal Info

Abbrev

wahana

Publisher

Subject

Civil Engineering, Building, Construction & Architecture Earth & Planetary Sciences Engineering Transportation

Description

Wahana Teknik Sipil: Jurnal Pengembangan Teknik Sipil or Civil Engineering Forum: Journal of Civil Engineering Development is a medium of communication and dissemination of research results, case studies, and scientific reviews (applied) to scientists and practitioners in the field of Civil ...