Process of monitoring and controlling projects requires data evaluation activities in the order to findout whether the project is in accordance with the plan to avoid an incompatibility between theplanning and the actual time. The failure of construction project almost reached the figure of 20% -40% which occurred in the project monitoring and controlling process. The purpose of this researchis analysis project performance with earned value management method at PLBN Project. Thisresearch was carried out by several stages: data collection, data processing and analysis. From theresults of the performance index analysis show that the project’s performance on the constructionproject is still not good. At week 16 the CPI and SPI values are 0.94 and 0.85. Both values can beinterpreted that the costs incurred are greater than planning and the implementation time is longerthan planning. The result of EAC is Rp. 2.423.695.294 with an estimated completion time is 21weeks which indicates that there is an additional 3 weeks of completion.