Perencanaan Pembangunan Smoking Area di Gedung Bitumen Pertamina Gresik Menggunakan Critical Path Method (CPM)

Enrico Ferdiansyah (Untag Surabaya 17 Agustus 1945)
Erni Puspanantasari Putri (Universitas 17 Agustus 1945 Surabaya)



Article Info

Publish Date
10 Apr 2026

Abstract

Bitumen Plant Gresik operated by PT Pertamina Patra Niaga does not yet have a dedicated smoking area at its office, despite the oil and gas environment carries a high fire risk. This study aims to plan the smoking area construction using the Critical Path Method (CPM) supported by Microsoft Project to determine the duration, critical path, and total project cost. The data used cover 20 work activities along with their durations, predecessors, volumes, and unit prices. Results show the project duration is 59 calendar days (1 February to 31 March 2026), with three parallel critical paths covering foundation, column, roster, flooring, anti-heat sticker, decorative elements, and site cleaning. The total project cost reaches IDR 255,850,000 (excluding 11% VAT), with the largest share of 84.53% allocated to structural and architectural work. These findings may serve as a project control baseline in oil and gas industrial settings.

Copyrights © 2026






Journal Info

Abbrev

jutin

Publisher

Subject

Decision Sciences, Operations Research & Management Energy Engineering Industrial & Manufacturing Engineering Mechanical Engineering

Description

Jurnal Teknik Industri Terintegrasi merupakan jurnal yang dikelola oleh Program Studi Teknik Industri Fakultas Sains dan Teknologi Universitas Pahlawan Tuanku Tambusai yang menjebatani para peneliti untuk mempublikasikan hasil penelitian di bidang ilmu teknik dan teknik industri mencakup proses ...