The Isimu Solar Power Plant (PLTS) has been constructed for the Gorontalo power system. This plant is directly interconnected to the Isimu Substation bus via a 20 kV distribution line. This interconnection alters the system's power flow and impacts its stability. Consequently, an analysis of the main generation system's performance under steady-state conditions—considering system disturbances—was conducted for both pre- and post-interconnection scenarios. The Isimu PLTS interconnection improved the voltage profile at each substation bus by an average of 1.06% and resulted in minimal power losses of 0.43%, thereby enhancing overall system performance. During short-duration disturbances, the Gorontalo power system remained stable; following a disturbance, the generator rotor angle returned to normal operation one second faster than in the pre-interconnection state.