The provision of roads and bridges fulfills the mandate of Law No. 2 of 2022 and constitutes a crucial public right for community mobility. The delayed completion of the Sei Musam Bridge in Langkat Regency from 2024 to 2026 has hindered basic service access for 44 households, affecting agricultural distribution, education, and public safety. This qualitative empirical-juridical study analyzes the fulfillment of this right under Law No. 2 of 2022 and the perspective of Siyasah Dusturiyyah, through interviews and observation of affected communities and relevant agencies. Findings show that obstacles stem from unresolved administrative harmonization and authority transfer between the North Sumatra Provincial Government and the Langkat Regency Government, requiring collaborative coordination between levels of government. From the Siyasah Dusturiyyah perspective, leadership policy must prioritize public welfare; the instrument of ta'zir mali offers an objective solution to encourage contractor compliance and accelerate infrastructure recovery