Venus: Jurnal Publikasi Rumpun Ilmu Teknik
Vol. 4 No. 4 (2026): Venus: Jurnal Publikasi Rumpun Ilmu Teknik

Evaluasi Waktu dan Biaya Proyek Konstruksi Menggunakan Kombinasi Metode Precedence Diagram Method dan Program Evaluation and Review Technique: Studi Kasus Pembangunan Ruang Kelas SMK Sore Tulungagung

Deni Cahya Saputra (Universitas Islam Balitar)
Hangga Prima Setiawan (Universitas Islam Balitar)
Heru Hendri Iswanto (Universitas Islam Balitar)



Article Info

Publish Date
31 Aug 2026

Abstract

Inaccurate project planning can lead to delays and cost overruns, as occurred in the classroom-building project at SMK Sore Tulungagung, which experienced a slowdown in work progress during Phase 1 (structural work) and Phase 2 (architectural work). This study aims to analyze time planning, the critical path, project completion probability, and time and cost efficiency using a combination of the Precedence Diagram Method (PDM) and the Program Evaluation and Review Technique (PERT), through a quantitative descriptive-analytical case-study approach. The results show that the combined PDM-PERT method reduced the duration of Phase 1 from 91 to 85 days (6.59% efficiency) and Phase 2 from 140 to 120 days (14.29% efficiency), with a completion probability of 99.99% (Z = 4.14) and 100% (Z = 11.36) respectively. Application of the combined method also produced a total cost saving of IDR 87,225,902.97 (12.02%). These findings prove that the combined PDM-PERT method is effective as a tool for planning and controlling the time and cost of construction projects.

Copyrights © 2026






Journal Info

Abbrev

Venus

Publisher

Subject

Automotive Engineering Chemical Engineering, Chemistry & Bioengineering Civil Engineering, Building, Construction & Architecture Computer Science & IT Engineering

Description

Engineering Science Clump. include the sub-groups of Civil Engineering and Spatial Planning, Industrial Engineering, Electrical and Computer Engineering. The Research Journal of the Engineering Science ...