SCHEDULING STUDY USING THE PDM METHOD IN THE PIANGGU-LALAP ROAD RECONSTRUCTION PROJECT (SUPPORTING THE FOOD ESTATE - DAK) IN AWANG DISTRICT, EAST BARITO REGENCY, CENTRAL KALIMANTAN

Rika Sapitri (Civil Engineering Study Program, Lambung Mangkurat University)
Eliatun Eliatun (Civil Engineering Study Program, Lambung Mangkurat University)



Article Info

Publish Date
08 Sep 2026

Abstract

The Pianggu-Lalap Road Reconstruction Project in Awang District, East Barito Regency, is a district road project by the PUPR Office. Initially, scheduling only used the S-curve without considering the relationship between activities, which caused delays. This research reconstructs the schedule using the Precedence Diagram Method (PDM) through the stages of WBS, duration determination, activity linkage analysis, and scheduling with Microsoft Project 2019. The results are displayed in Gantt Chart and Network Diagram, with a total duration of 142 days, from July 4 to November 19, 2024 Keywords: Scheduling, Precedence Diagram Method (PDM), Microsoft Project 2019

Copyrights © 2026






Journal Info

Abbrev

crc

Publisher

Subject

Civil Engineering, Building, Construction & Architecture

Description

Jurnal internasional bidang teknik sipil seperti : sumberdaya air, struktur bangunan, mekanika tanah, transportasi dan manajemen konstruksi. ...