Cost And Productivity Analysis Of Installing 40 X 60 X 120 U-Ditches Using Heavy Equipment Compared To Manual Methods In Sumur Welut, Lakarsantri District, Surabaya: Analisis Biaya Dan Produktivitas Pemasangan U-Ditch 40 X 60 X 120 Menggunakan Alat Berat Dibandingkan Metode Manual Di Sumur Welut, Kec. Lakarsantri, Surabaya

Fila Atma Jalu Eka Irawan (Program Studi Teknik Sipil, Universitas Muhammadiyah Sidoarjo)
Atik Wahyuni (Program Studi Teknik Sipil, Universitas Muhammadiyah Sidoarjo)



Article Info

Publish Date
13 Oct 2026

Abstract

General Background Drainage infrastructure development plays a crucial role in mitigating hydrometeorological disasters and supporting sustainable urban resilience in metropolitan areas like Surabaya. Specific Background The installation of precast concrete U-ditches is widely implemented in urban drainage projects, yet contractors frequently face strategic dilemmas when choosing between manual labor and heavy equipment methods. Knowledge Gap Although mechanical methods are generally assumed to be superior, detailed empirical evaluations comparing direct costs and work productivity per unit between manual and heavy equipment approaches under identical field conditions remain limited. Aims This study aims to analyze and compare work productivity, direct costs, and cost efficiency between the heavy equipment method utilizing an excavator and forklift and the manual method for installing 40 x 60 x 120 cm U-ditches in the Sumur Welut drainage project, Surabaya. Results Field evaluations indicate that the heavy equipment method achieves a daily productivity of 18 units, which is significantly higher than the 2.5 units achieved by the manual method, while yielding a direct cost of Rp 221,667 per unit that proves more economical and time-saving. Novelty This research provides empirical evidence that mechanization successfully compensates for higher daily investment through economies of scale and accelerated schedule completion in urban drainage construction. Implications The findings serve as a reliable quantitative reference for project managers and planners in selecting optimal construction methods to enhance time and cost efficiency in similar infrastructure projects. Key Findings Highlights The heavy equipment method achieves a daily productivity of 18 units, significantly outperforming the manual method's 2.5 units. Mechanized U-ditch installation provides superior time efficiency, reducing project duration from twelve days down to six working days. Despite higher initial daily equipment rental expenses, high-volume production makes the mechanized approach highly cost-effective per unit. Keywords Cost Analysis, Productivity, U-ditch, Heavy Equipment, Manual Method

Copyrights © 2026






Journal Info

Abbrev

ijins

Publisher

Subject

Computer Science & IT Education Engineering Law, Crime, Criminology & Criminal Justice

Description

Indonesian Journal of Innovation Studies (IJINS) is a peer-reviewed journal published by Universitas Muhammadiyah Sidoarjo four times a year. This journal provides immediate open access to its content on the principle that making research freely available to the public supports a greater global ...