cover
Contact Name
Henriette D. Titaley
Contact Email
henriette.titaley@polnam.ac.id
Phone
+6282188099397
Journal Mail Official
henriette.titaley@polnam.ac.id
Editorial Address
Jl. Ir. M. Putuhena, Wailela-Rumah Tiga, Kota Ambon Provinsi Maluku
Location
Kota ambon,
Maluku
INDONESIA
Jurnal Agregate
ISSN : -     EISSN : 29645158     DOI : https://doi.org/10.31959/ja.v2i1
Core Subject : Engineering,
Jurnal Agregate adalah Jurnal yang memberikan informasi ilmiah tentang perkembangan ilmu pengetahuan dan teknologi bidang Struktur, Bahan Bangunan Dan Kegempaan, Teknik Sumber Daya Air, Transportasi, Management Konstruksi, Geoteknikal, Teknik Pantai Dan Tsunami.
Articles 50 Documents
Search results for , issue "Vol. 3 No. 1 (2024): Maret" : 50 Documents clear
PERENCANAAN ANGGARAN BIAYA DAN WAKTU PELAKSANAAN PEKERJAAN STRUKTUR LAUNDRY ZEST HOTEL AMBON BERDASARKAN AHSP PERMEN PU 28/PRT/M/2016 Pattikawa, Elena Julian; Saleh, La Mohamat; Gaspersz, Willem
Journal Agregate Vol. 3 No. 1 (2024): Maret
Publisher : Jurusan Teknik Sipil

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.31959/ja.v3i1.1802

Abstract

To restore the level of project progress according to the planned cost and time, appropriate planning is needed to obtain optimal project costs and duration. These parameters are planned to achieve project targets within cost and time constraints. The Zest Hotel Ambon Laundry construction project reviewed by the author is a privately funded project with a tentative implementation time so that there are no binding elements in terms of both cost and project implementation time. For this reason, the author will plan the budget and implementation time based on AHSP Minister of Public Works Regulation 28/PRT/M/2016. The aim of this research is to obtain more accurate estimates so that the project can be managed well, can achieve the desired goals, and stay within the budget and time limits that have been set. From the results of budget planning calculations for the implementation of the Zest Hotel Ambon Laundry structure based on AHSP Minister of Public Works Regulation 28/PRT/M/2016, the cost was IDR 1,193,329,721.76. Meanwhile, planning the project implementation time based on the standard AHSP coefficient of PU Ministerial Decree 28/PRT/M/2016 using the CPM method and the application of Microsoft project software, the total project duration was 172 calendar days
ANALISIS PENERAPAN METODE LINE OF BALANCE (LOB) PADA PROYEK PEMBANGUNAN RUANG KELAS BARU MADRASAH IBTIDAIYAH NEGERI 5 MALUKU TENGAH Lessy, Gheisberth Tontji; Jamlaay, Octovianus; Saleh, La Mohamat
Journal Agregate Vol. 3 No. 1 (2024): Maret
Publisher : Jurusan Teknik Sipil

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.31959/ja.v3i1.1803

Abstract

Construction projects that have repetitive or repetitive work packages such as housing, school buildings, apartments, hotels, highways or manufacturing industry projects require a project scheduling method that is able to accommodate continuous and well scheduled resource requirements without the occurrence of a hitch. In the New Classroom Development Project for Madrasah Ibtidaiyah Negeri 5 Central Maluku, the author reviewed using the S – Curve scheduling method and experienced delays in implementation due to rainy weather, delays in material mobilization and lack of manpower, so the author will analyze scheduling with a special method for repetitive work, namely by using the methodLine of Balance (LoB). Method Line of Balance (LoB) is a project scheduling method that can provide productivity levels and duration information in graphical format and can show activity progress, and can detect potential disturbances or conflicts in work items to be worked on. This research stage is obtained from the datatime schedule a plan that aims to redraw to detect conflicts in work items. From the results of the research, the use of the methodLine of Balance (LoB) simplification of repetitive work activities for structural work and architectural work from the first floor to the second floor makes it easier to analyze which is then depicted in a line chart and the results of the analysis show the methodLine of Balance(LoB) can detect conflicts or lines of work activity that intersect, among others, Structural Work of the second floor intersects with Wall and Plastering of the first floor, Wall and Plastering of the second floor intersects with Ceiling Works of the second floor, Sanitair Works of the first floor intersects with Aluminum Works Composite Panel (ACP) on the first floor and from the calculation results obtained the final scheduling duration of 84 days or 12 weeks and from the results of the analysis showed that the LoB method was effective in its use in the New Classroom Development project at Madrasah Ibtidaiyah Negeri 5 Central Maluku because it was able to detect disturbances in the Curve – S of LoB chart depiction
ANALISA PERHITUNGAN RENCANA ANGGARAN BIAYA DAN PENERAPAN MANAJEMEN WAKTU PADA PELAKSANAAN PROYEK REHAB RUMDIS HUBDAM XVI/PATTIMURA – AMBON Matahelumual, Mygthsico Joana; Jamlaay, Octovianus; Titaley, Henriette Dorothy
Journal Agregate Vol. 3 No. 1 (2024): Maret
Publisher : Jurusan Teknik Sipil

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.31959/ja.v3i1.1818

Abstract

The rehabilitation of the Hubdam XVI/Pattimura Ambon Official Residence was carried out as an improvement to building facilities that were damaged by the movement of the earth's plates (earthquake). Construction work consists of planning a cost budget plan to planning a project implementation schedule. This study aims to calculate the cost budget plan (RAB) and determine which work is included in the critical trajectory. The building cost budget plan (RAB), identifies each work item in the project being calculated based on the 2019 SNI analysis and applies the Critical Path Method (CPM) method. The cost budget plan (RAB) for the Hubdam XVI / Pattimura Ambon official residence rehabilitation project for the total price amount is IDR 2,725,577,390.90 rounded up to IDR 2,725,577,000.00, - and the work items that are passed through the critical path are preparation work, foundation and concrete work, roof work, ceiling work, to painting work.
PEMANENAN AIR HUJAN SEBAGAI ALTERNATIF SUMBER AIR BERSIH UNTUK KEBUTUHAN MASYARAKAT DESA MESIAPI KABUPATEN MALUKU BARAT DAYA Nirahua, Efata; Betaubun, Renny James; Titaley, Henriette Dorothy
Journal Agregate Vol. 3 No. 1 (2024): Maret
Publisher : Jurusan Teknik Sipil

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.31959/ja.v3i1.1941

Abstract

Rainwater is harvested through a simple system commonly called Rain Water Harvesting. The purpose of this research is to determine the quality of rainwater to be harvested, the potential discharge that can be utilized, and the design of the PAH system for Mesiapi Village, Southwest Maluku Regency. The method of determining the quality of rainwater is done by collecting rainwater and then testing it in the laboratory. Analysis of rainfall frequency using continuous probability, namely the distribution of gumbel and log person III then tested the probability distribution using the Chi square test, to determine the discharge of clean water that can be harvested, after that planning the design and cost budget for making a recervoir tub. The results of water quality testing show a pH value of 8.11; Temperature 24.4°C; and TDS 22.9 mg/l. The highest rainfall value in Mesiapi village for 10 years with the highest rainfall level occurred in 2020, namely 260 mm. The rainfall return period is 2 years with a rain duration of 2 hours, with the Log Person III distribution obtaining a rainfall plan value of 7.857 mm/hour and a discharge of 61 lt/det. The draft cost budget obtained from the calculation for the construction of a recervoir (reservoir) in Mesiapi village with a plan for 2 reservoirs is IDR 665,284,000.
PENGARUH PRODUKTIVITAS TENAGA KERJA TERHADAP PROYEK PEMBANGUNAN GEDUNG RUANG KELAS BARU (RKB) MADRASAH IBTIDAIYAH NEGERI 5 MALUKU TENGAH Nahumarury, Aulia; Serang, Rudy; Abdin, Maslan
Journal Agregate Vol. 3 No. 1 (2024): Maret
Publisher : Jurusan Teknik Sipil

Show Abstract | Download Original | Original Source | Check in Google Scholar

Abstract

Construction  projects are one of the of the activities where the results of the work are influenced by the productivity of the workforce. Activities in construction projects are interrelated, so that if one activity is late it will hinder other activities in the field. Likewis, construction activities are complex work and require more attention in their implementation. The aim of  this research is to obtain what factors influence labor productivity and determine the presentation of the influence of independent variables on labor productivity in the classroom building (RKB) construction project of madrasah ibtidaiyah negeri 5 maluku tengah. The analysis method used in the research this is with the help of the SPSS version 26 program. In the  new classroom building (RKB) Construction project of madrasah ibtidaiyah negeri 5 maluku tengah there are several factor that influence labor productivity including labor, material, weather and environmental factors and the presentation of the influence of independent variables on labor productivity, which is 88.1% and the remaining 11.9% was influenced by other variables not tested in this study.
ANALISIS KINERJA STRUKTUR ATAS BANGUNAN RTMC POLDA MALUKU MENGGUNAKAN METODE STATIC NON-LINEAR Markus, Leviona; Frans , Pieter Lourens; Hutubessy , Vector R. R
Journal Agregate Vol. 3 No. 1 (2024): Maret
Publisher : Jurusan Teknik Sipil

Show Abstract | Download Original | Original Source | Check in Google Scholar

Abstract

Ambon City is one of the cities in Moluccas which is also one of the earthquake-prone areas which is classified in earthquake zone 5. Several structural elements of the Moluccas Police RTMC building in the realization of fieldwork were not by the planning results. The research aimed to produce displacement values ​​and obtain the performance of the structural of the Maluku Regional Police RTMC building against earthquake forces after being analyzed by non-linear static analysis with the help of SAP2000 v.22. Research shows that the movement between floors is still safe because it does not exceed the drift limit of 30 mm where the largest displacement in the x direction occurs due to a dynamic earthquake (DX) on the roof floor, about 10.443 mm, and the largest displacement in the y direction occurs due to loads due to dynamic earthquakes (DY) on the roof floor about 28.514 mm. The performance evaluation for the XZ direction is still in a safe condition because the plastic hinge distribution scheme does not show structural members that pass the immediate occupancy (IO), and happen strong column weak beams occur if the loading step is enlarged, this is indicated by the absence of column elements that achieve IO performance. The performance of the YZ direction is still in a safe condition because the plastic hinge distribution scheme does not show that the structural members pass the IO performance and happen strong column weak beams occur when the loading step is increased.
PENGARUH PENGGUNAAN SERBUK KACA SEBAGAI BAHAN PENGGANTI SEBAGIAN AGREGAT HALUS TERHADAP KUAT TEKAN BETON Ode, Titin; Sahusilawane, Tonny; Marantika , Meyke
Journal Agregate Vol. 3 No. 1 (2024): Maret
Publisher : Jurusan Teknik Sipil

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.31959/ja.v3i1.1981

Abstract

Some of this bottle waste is directly disposed of into open land without any treatment. One alternative use for beer glass bottle waste is to make it a substitute for fine aggregate in concrete mixture, by processing it into pounded glass powder until it smoothly passes filter no. 12. The addition of glass powder by 0%, 2.5% and 5%. The concrete test specimen measures 15×15×15 cm and is planned according to the SNI method 03-2834- 2000. The test parameters carried out are in the form of a slump test and concrete compressive strength with a compressive strength standard of 200 Kg / cm² at a concrete age of 7 days. The results obtained in this study were the compressive strength of concrete the percentage of using 0% glass powder of 264.29 kg / cm2, 2.5% of 252.26 kg / cm2, and 5% of 192.80 kg / cm2. Slump test values percentage 0% 8 cm, 2.5% 8.8 cm and 5% 10.8 cm. So it can be concluded that the use of glass powder as a substitute for some fine aggregate against concrete compressive strength affects the quality of concrete compressive strength with a variation of 2.5% can increase the compressive strength of concrete greater than normal concrete. However, the more glass powder, the lower the compressive strength of the concrete obtained. While the use of glass powder as a substitute for some fine aggregates affects the value of the slump test, the more the percentage of the use of glass powder in the concrete mixture, the higher the slump value.
TINJAUAN FONDASI TIANG PANCANG PADA BANGUNAN RTMC POLDA MALUKU Lestaluhu, Apriyanti; Frans, Pieter Lourens; Titaley, Henriette Dorothy
Journal Agregate Vol. 3 No. 1 (2024): Maret
Publisher : Jurusan Teknik Sipil

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.31959/ja.v3i1.1993

Abstract

The foundation of the RTMC Polda Maluku building has changed in the length of the piles used during implementation that is not in accordance with the plan, raising the question of whether the pile foundation with its carrying capacity is able to accept the load working on it. The purpose of this study is to obtain the results of calculating the carrying capacity and lowering of pile foundations in the RTMC building of the Maluku Regional Police using the Meyerhoff method based on Sondir test result data, SPT and laboratory test result data. This study shows that the calculation of the ultimate carrying capacity obtained the ultimate carrying capacity value of single piles from sondir data of 305.6 tons, and SPT data of 595.2 tons and laboratory data of 150.88 tons. This shows that the largest carrying capacity results are based on SPT data, then followed by sondir data and the smallest is the carrying capacity based on laboratory data results. The calculation of the decline in the pile foundation with the number of 2 piles shows a single decrease of 0.0062 m and a decrease in the pile group of 0.015 m and the result of the decline in the pile foundation with a total of 3 piles shows a single decrease of 0.0063 m and a decrease in the group of 0.015 m. This shows that the decrease in the foundation of 2 poles and 3 poles is smaller than the allowable decrease of 0.15 m so that the decrease is declared safe.
PENGARUH PENAMBAHAN PUTIH TELUR TERHADAP KUAT TEKAN BETON Tarantein, Debora; Sahusilawane, Tonny; Apalem, Delvia Rimesye
Journal Agregate Vol. 3 No. 1 (2024): Maret
Publisher : Jurusan Teknik Sipil

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.31959/ja.v3i1.2050

Abstract

The use of concrete as a building material has long been known in Indonesia. Basically, concrete is defined as a mixture of other hydraulic cement, fine aggregate, coarse aggregate and water with or without additional ingredients (admixture) which form a solid mass. Historically, egg white itself has been used as a mixture in concrete. Egg white contains calcium carbonate (CaCO3), magnesium oxide (Mg), iron oxide (Fe2O3) and phosphorus pentoxide (P2O5), which are also contained in cement. Egg white will be an added ingredient in the concrete mixture in this test with a percentage of added material used of 0%, 2% and 2.3% of the cement weight. The concrete test object is made in the form of a cube with dimensions of 15×15×15 cm and is made according to the SNI 03-2834-2000 method. The parameters to be tested are the slump test and the compressive strength of the concrete with a standard compressive strength of 200 Kg/cm² at a concrete age of 7 days. The results obtained in this research were that the compressive strength of concrete with 0% egg white added was 223.7 kg/cm2, 2% was 181,8 kg/cm2, and 2.3% was 221,1 kg/cm2. The slump test percentage values ​​are 0% = 9 cm, 2% = 10.8 cm and 2.3% = 8 cm. So it can be concluded that the use of egg white as an added material has an effect on compressive strength, because the more egg white added material in the concrete, the stronger the compressive strength of the concrete and the resulting slump test. It can be seen from the use of 2% added material which produces a compressive strength of 181,8 kg/cm2 and 2.3% yields 221,1 kg/cm2.
PERENCANAAN DINDING PENAHAN BADAN JALAN TIPE GRAVITASI STUDI KASUS : PENINGKATAN JALAN HARUKU-OMA RUAS JALAN ABORU-HARUKU Yusuf, Densya; Hutubessy, Vector R. R; Soumokil, Musper David
Journal Agregate Vol. 3 No. 1 (2024): Maret
Publisher : Jurusan Teknik Sipil

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.31959/ja.v3i1.2082

Abstract

The condition of the road in Haruku Village experienced a landslide on the road to Oma Village which was 15 meters long and the landslide depth was 5 meters. The retaining wall on the road body is a construction structure built to stabilize the pressure on the road body and certain soil conditions. In general, retaining walls are used in natural slope areas and artificial slope areas as well as areas that are prone to landslides. The aim of this planning is to obtain the distribution of lateral pressure that works and the stability of the road body retaining walls that are safe against shear forces, overturning forces and collapse in the bearing capacity of the road body in Haruku Village, Haruku Island District, Central Maluku Regency. The methods used are the Rankine method regarding active earth pressure and passive earth pressure on road retaining walls and the Terzaghi method regarding soil bearing capacity. The results of the calculation of the lateral pressure distribution acting on the retaining walls of the Haruku Village road are the active earth pressure distribution value, namely the flat active soil coefficient value for flat soil (Ka), namely 0.33, the active soil pressure value for non-cohesive soil (Pa), namely 81.72 kN and the value The passive earth pressure coefficient for flat soil (Kp) is 3. The passive earth pressure coefficient for non-cohesive soil (Pp) is 42.36 kN. From the results of the safety factor calculation, the value of wall stability against shear is 2.80>1.5 (Safe), the wall stability value against overturning is 2.70>1.5 (Safe) and the safety factor against collapse of the bearing capacity is 15.67> 3 (Safe).