Slope Stability for Landslide in Road Preservation Working Packages Ende-Wolowaru and Junction-Kelimutu STA 8+425 Frans Andre Sasarari; Yudhi Lastiasih; Herman Wahyudi; Agustinus Junianto
Journal of Infrastructure & Facility Asset Management Vol 6 (2024): Special Issue 2 : Journal of Infrastructure & Facility Asset Management
Publisher : Departemen Teknik Sipil, Institut Teknologi Sepuluh Nopember

Show Abstract | Download Original | Original Source | Check in Google Scholar

Abstract

On the Ende-Kelimutu national road section at STA 8+425, according to the identification and field survey, the landslide that occurred at this point was caused by high rainfall intensity and geological factors of the slope. As the road supervisor, the Balai Pelaksanaan Jalan Nasional (BPJN) of East Nusa Tenggara has designed a landslide treatment using a combination of cantilever walls and drilled poles. Soil investigation data at STA 8+425 shows that the slope is dominated by sand with N-SPT values above 15 to a depth of 14.45 meters. When making design improvements, a number of rainfall data from several weather observation stations are needed, in order to determine the effect of rainwater infiltration on the landslides that occur. This study aims to determine the influence of rainwater infiltration on the occurrence of landslides at the study site, where the results of the analysis conducted with Geostudio prove the truth. Modeling with the combination of SEEP/W and SLOPE/W, the FS value before the landslide was 2.302 and then decreased to 0.35 during the landslide.
Effectiveness And Stability Analysis Of Embankment Using Lightweight Embankment On Pasuruan - Probolinggo Toll Road Project Section 4, Indonesia Ruri Febri Ritwandanu; Herman Wahyudi; Yudhi Lastiasih; Hamim Mufijar
Journal of Infrastructure & Facility Asset Management Vol 6 (2024): Special Issue 3 : Journal of Infrastructure & Facility Asset Management
Publisher : Departemen Teknik Sipil, Institut Teknologi Sepuluh Nopember

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.12962/jifam.v6i0.19965

Abstract

The Pasuruan-Probolinggo Section 4 Toll Road project which has a length of 12.04 km is dominated by silty clay - clay. In addition to soft soil, there are other problems in the construction of the Pasuruan - Probolinggo Section 4 toll road, namely the limited availability of embankment soil material around the project site and the location of the quarry which is quite far away. In addition, when relying on embankment material from the quarry, the weather factor will play a very important role when the weather is rainy then the activity in the quarry stops, the targeted embankment volume is not met and the progress of work on that day is not achieved. Therefore, there is a need for alternative reinforcement of embankments other than soil embankments from quarries that are safe and light enough. Based on the existing problems, this research will conduct a comparative study of toll road embankment design with 3 different types of materials, namely: Conventional soil embankment compared with lightweight embankment in the form of EPS-Geofoam material and foam mortar material. This research will use Plaxis 2D program. The results of this research will determine alternative embankment materials that can be applied to soft subgrade so that overall stability and hydrostatic uplift requirements can be met. This research is expected to be a reference in planning the construction and improvement of the subgrade of the Pasuruan-Probolinggo Section 4 toll road and other toll roads using EPS geofoam embankment and foam mortar
Comparation of Limit Equilibrium Method (LEM) 2D on Safety Factor and Embankment Reinforcement Aisiyah Pramaisela Hapsari; Yudhi Lastiasih
Journal of Infrastructure & Facility Asset Management Vol 6 (2024): Special Issue 3 : Journal of Infrastructure & Facility Asset Management
Publisher : Departemen Teknik Sipil, Institut Teknologi Sepuluh Nopember

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.12962/jifam.v6i0.19966

Abstract

The analysis of slope stability is crucial during embankment planning to ensure safety and prevent landslides. A stable slope ensures the safety of surrounding infrastructure, minimizing the risk of damage. Therefore, with slope stability analysis can manage and maintain infrastructure assets. The primary method used to evaluate slope stability is the Limit Equilibrium Method, frequently employed in a 2D framework using various applications such as Plaxis LE and Geostudio. Using diverse applications for analysis can yield varying safety factors, influencing the required reinforcement. Hence, this study analyzed safety factors and the necessary geotextile reinforcement for embankments on soft soil featuring distinct heights, slopes, and widths in 2D. The analysis was performed using the Plaxis LE application, and the results were subsequently compared with those obtained from the Geostudio application. This research shows that the results of the embankment safety factors with the Plaxis LE application are different from those of the embankment safety factors with Geostudio, resulting in different embankment geotextile reinforcement namely the need for Plaxis LE geotextile reinforcement = 0.7 Geostudio geotextile reinforcement.
The Effect of Prefabricated Vertical Drain Length on Soft Soil Settlement (Case Study: The North Ring Road of Lamongan STA. 3+200) Henniko Okadha; Herman Wahyudi; Yudhi Lastiasih; Sifa’ Udukha
Journal of Infrastructure & Facility Asset Management Vol 7 (2025): Special Issue 3 : Journal of Infrastructure & Facility Asset Management
Publisher : Departemen Teknik Sipil, Institut Teknologi Sepuluh Nopember

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.12962/jifam.v7i3.4429

Abstract

The North Ring Road of Lamongan Project Section I, which stretches from Sta. 0+000 to Sta. 3+265, is indicated to be built on soft silt soil. This paper discusses the effect of Prefabricated Vertical Drains (PVDs) length on the amount of settlement that occurs in soft soil. The method used was to compare the installation of PVDs at a quarter, half and three quarters of the thickness of the compressible soil layer. The varying lengths of PVDs were modeled on PLAXIS2D software. The results show that the longer PVDs are installed in the compressible soil, the greater settlement occurs.
Analysis of PVD Installation Methods Due to Limited Vertical Clearance in the Lamongan North Ring Road Construction Project Section 1 STA 0+400 to STA 0+426 Fanny Rumintha Br Barimbing; Yudhi Lastiasih; Herman Wahyudi; Sifa` Udukha
Journal of Infrastructure & Facility Asset Management Vol 7 (2025): Special Issue 3 : Journal of Infrastructure & Facility Asset Management
Publisher : Departemen Teknik Sipil, Institut Teknologi Sepuluh Nopember

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.12962/jifam.v7i0.22485

Abstract

The construction of the Lamongan North Ring Road is planned to be built on softsoil. Based on the results of the soil investigation, it is known that the subgradecondition is classified as soft to very soft soil with a depth of 18 meters. One of theproblems of this very soft soil is the settlement. Therefore, the National RoadImplementation Agency of East Java - Bali Region conducted subgrade improvementusing preloading combined with Prefabricated Vertical Drain (PVD). The configurationof the PVD installation is 18 meters deep with a triangular pattern and the distancebetween PVDs is 1 meter. To stake the PVDs 18 meters deep, a piling rig with aminimum height of 24 meters is required. In the STA 0+400 to STA 0+426 section thereis a 150 kV Lamongan - Paciran High Voltage Air Line (SUTT) cable crossing the roadwith a conductor to platform distance of 18 meters. The existence of this cable is achallenge in the PVD driving as deep as 18 meters. Therefore, this journal will analyzethe PVD piling implementation method that can be carried out in this segment. Themethod carried out in this study is to start with the collection of secondary data such asshop drawings as a reference for the implementation of work in accordance with theplanned design. Based on the design plan, an implementation method that can beapplied to limited vertical clearance conditions is obtained. Based on the results of theresearch, an 18-meter deep PVD installation method was obtained that can be applied tolimited vertical clearance conditions in the Lamongan North Ring Road constructionproject Section 1 STA 0+400 to STA 0+426. In addition, it was also found that the timerequired was 34.75 minutes to stake 1 PVD point using the pulled hole PVD method.
Parametric Study of Embankment Stability And Geotextile Reinforcement On Soft Soil Mirza Syah Alam; Herman Wahyudi; Yudhi Lastiasih; Yusrizal Kurniawan
Journal of Infrastructure & Facility Asset Management Vol 7 No 1 (2025): Journal of Infrastructure & Facility Asset Management
Publisher : Departemen Teknik Sipil, Institut Teknologi Sepuluh Nopember

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.12962/jifam.v7i1.22414

Abstract

The Semarang - Demak Toll Road Construction Project Section 1B has a length of 6.736 km, starting from STA. 1+578 to 8+314. There is a zone that has the highest embankment, namely zone N at STA. 4+200 to 4+600. However, based on soil investigation data, it is known that the Semarang - Demak Toll Road Construction Project Section 1B has a very thick compressible layer, which reaches a depth of 50 m. This makes the Semarang - Demak Toll Road Construction Project Section 1B face various challenges of construction on soft soil. The purpose of this research is to determine the Safety Factor (SF) value and the appropriate configuration of geotextile reinforcement requirements in an embankment with variations in compressible layer thickness, embankment height and embankment slope, especially in the case study of zone N with STA. 4+200 - 4+600. This research will be processed using the Limit Equilibrium Method (LEM) with the GEO5 auxiliary program. Based on the results in this study, it is known that the variation of compressible layer thickness does not have a significant influence on the calculation of the Safety Factor and geotextile reinforcement configuration. However, the variation of embankment height leads to the conclusion that the higher the embankment, the lower the Safety Factor. The variation of embankment slope also concluded that the steeper the embankment, the lower the Safety Factor. In addition, it is also known that the higher the embankment, the higher the number of geotextile reinforcement requirements and the steeper the embankment, the higher the number of geotextile reinforcement requirements. After making a nomogram of the relationship between these variations and implementing it on the case study, it is known that the embankment in Zone N of the Semarang - Demak Toll Road Construction Project Section 1B has a Safety Factor value of 0.42 and requires 33 layers of geotextile reinforcement with a tensile strength of 200 kN/m, a spacing of 25 cm between layers, and a Reduction Factor value of 1.65.
A Study of Pile Displacement in Soft Soil: The Case of Semarang - Demak Toll Road Construction Package 1B Novera Sagita; Herman Wahyudi; Yudhi Lastiasih; Yusrizal Kurniawan
Journal of Infrastructure & Facility Asset Management Vol 7 No 1 (2025): Journal of Infrastructure & Facility Asset Management
Publisher : Departemen Teknik Sipil, Institut Teknologi Sepuluh Nopember

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.12962/jifam.v7i1.22417

Abstract

In the construction package of Semarang-Demak Toll Road 1B, an elevated bridge is planned to be built using a pile foundation of 56 pieces with a diameter of 1.0 m installed at a depth of 68m. The soil conditions at the site are very soft to medium clay and silt. During the excavation of the footing work, there was a displacement of 11 piles. This study aims to analyze the pile displacement behavior at each work sequence due to the influence of excess pore pressure and excavator distance near the pile. The pile displacement behavior was modeled using a Finite Element Method (FEM) based program, Plaxis 2D. Piles are modeled using an elastic constitution model to obtain deformation results that match the actual conditions in the field. While the soil is modeled using the Mohr Coulomb soil constitutive model on the embankment soil and Soft Soil on the original soil. The analysis was conducted to determine the lateral displacement of poles in field conditions at each sequence of work on unconsolidated soil with/without an excavator load of 15 kN. The results showed that by conditioning the soil at 90% consolidation degree (U90%) can reduce the lateral displacement value of the pile by 95.96% at the 4 m deep excavation stage compared to the unconsolidated soil. By placing the excavator 6.5 m away from the piles, it can reduce the lateral displacement that occurs by 20.96% compared to the existing position of 3.5 m from the piles.