Astrid Sulistya Azahra
Doctoral of Mathematics Study Program, Faculty of Mathematics and Natural Sciences, Universitas Padjadjaran, Sumedang 45363, Indonesia

Published : 2 Documents Claim Missing Document
Claim Missing Document
Check
Articles

Found 2 Documents
Search

Sustaining Composting Practice through Structured Monitoring Cards in Cinunuk Village, West Java Natasya Tamarysma Putri; Nurfadhlina Abdul Halim; Astrid Sulistya Azahra
International Journal of Research in Community Services Vol. 7 No. 3 (2026): International Journal of Research in Community Service (IJRCS)
Publisher : Research Collaboration Community (Rescollacom)

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.46336/ijrcs.v7i3.1357

Abstract

Household organic waste is the largest single component of Indonesia's national waste stream, and more than half of all municipal waste originates from households. Community service programs across Indonesia have responded by introducing household-scale composting technologies, particularly the Takakura method, and typically report favorable knowledge gains and short-term adoption rates. However, most of these programs evaluate success only immediately after training or during a brief mentoring period, leaving it unclear whether the newly adopted composting practice is actually sustained once the intervention team withdraws. This community service program was carried out in Cinunuk Village, Cileunyi District, Bandung Regency, West Java, and combined Takakura composting training with a low-cost Household Composting Monitoring Card and three scheduled follow-up visits at week 2, 4, and 8 to track practice sustainability alongside conventional knowledge and attitude indicators. Thirty housewife cadres participated in a program comprising needs assessment, socialization, hands-on training, monitoring, and evaluation. Results showed a substantial increase in composting knowledge, from a pre-test mean of 54.6 to a post-test mean of 86.3, a sustained Practice Sustainability Compliance rate of 76.7 percent by week eight, and a cumulative household organic waste reduction of approximately 47 percent. Compared with prior composting community service reports that do not track practice beyond the training period, this program demonstrates that a simple, paper-based monitoring instrument can meaningfully extend the durability of household composting behavior at negligible additional cost, offering a replicable model for other rural and peri-urban communities in Indonesia.
Quantitative Analysis of Risk Factors Causing Delays in Road Infrastructure Projects Using the SEM (Structural Equation Modeling) Method Riza Adrian Ibrahim; Astrid Sulistya Azahra; Nurnisaa binti Abdullah Suhaimi
International Journal of Quantitative Research and Modeling Vol. 7 No. 3 (2026): International Journal of Quantitative Research and Modeling (IJQRM)
Publisher : Research Collaboration Community (RCC)

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.46336/ijqrm.v7i3.1444

Abstract

Road infrastructure projects are vulnerable to schedule disruption arising from interacting managerial, resource, technical, financial, and external conditions. However, conventional delay studies often identify or rank individual factors without estimating their structural contribution. This study develops and tests an integrated model of seven risk dimensions affecting road infrastructure project delay using Structural Equation Modeling. An explanatory design was implemented through a cross-sectional survey of 260 professionals involved in road infrastructure projects. The measurement model was assessed using indicator loadings, Cronbach’s alpha, composite reliability, average variance extracted, and the Heterotrait–Monotrait criterion, while the structural model was evaluated through path coefficients, collinearity diagnostics, bootstrapping, and explanatory power. The measurement results demonstrated reliability, convergent validity, and discriminant validity across all constructs, with all 42 indicators retained. The structural model showed that Project Management Risk was the strongest predictor of Project Delay (β = 0.458, p < 0.001), followed by External Risk (β = 0.227, p = 0.0006), Human Resource Risk (β = 0.152), Financial Risk (β = 0.143), and Material Risk (β = 0.139). Technical/Design Risk and Equipment Risk did not demonstrate significant effects. Collectively, the seven risk dimensions explained 69.5% of the variance in Project Delay, with Project Management Risk contributing 43.6% of explained variance. The findings establish that road-project delays are principally associated with management and external conditions, supporting risk mitigation strategies that prioritize governance, coordination, monitoring, decision-making, and contingency planning.