METODE PELAKSANAAN PEKERJAAN PIERTABLE MENGGUNAKAN SISTEM BRACKET CONSOLE PADA JEMBATAN JUNCTION SEDYATMO TOL KATARAJA SEKSI 1 DIVISI INFRASTRUKTUR 1 DI KOTA JAKARTA UTARA, PROVINSI DKI JAKARTA Nurmala Dwiani; Erni Sari Lumban Toruan
SEMINAR TEKNOLOGI MAJALENGKA (STIMA) Vol 10 (2026)
Publisher : Universitas Majalengka

Show Abstract | Download Original | Original Source | Check in Google Scholar

Abstract

The development of toll road infrastructure plays an important role in improving regional connectivity, facilitating transportation, and supporting national economic growth. In bridge construction, particularly at junction areas with high elevations and limited working space, an effective and safe construction method is essential. The piertable, which connects the pier to the bridge superstructure, requires high construction accuracy. This study aims to describe the installation of the bracket console system, the implementation of piertable construction, and the challenges encountered during the construction process. The study was conducted through direct field observations, interviews and technical discussions with engineers and project supervisors, and a review of project documents, including working drawings and construction methods. The results show that the bracket console system provided stable and safe support for formwork and fresh concrete at an elevation of 13 m. The piertable construction was carried out systematically through reinforcement, formwork installation, concrete casting, curing, and prestressing in accordance with project specifications. Challenges such as reinforcement congestion, strand elongation deviation, and weather conditions were successfully addressed through proper supervision and quality control. Overall, the application of the bracket console system proved to be effective in improving construction efficiency, ensuring work safety, and maintaining the structural quality of the piertable.