ANALISIS METODE PELAKSANAAN PEMASANGAN EXPANSION JOINT TIPE STRIP SEAL PADA PROYEK PRESERVASI JEMBATAN LAYANG PEGAMBIRAN KOTA CIREBON Yoga Setyawan; Erni Sari Lumban Toruan
SEMINAR TEKNOLOGI MAJALENGKA (STIMA) Vol 10 (2026)
Publisher : Universitas Majalengka

Show Abstract | Download Original | Original Source | Check in Google Scholar

Abstract

Expansion joints play an important role in maintaining bridge performance by accommodating structural movements and preventing damage caused by traffic loads and environmental effects. This study aims to analyze the installation method of a strip seal expansion joint implemented in the Pegambiran Flyover Bridge Preservation Project, Cirebon City. A descriptive case study approach was employed using field observations, documentation, interviews, and project documents. The analysis focused on the installation sequence, including surface preparation, removal of the existing joint, installation of chemical anchors, retainer steel installation, rapid-setting grout casting, strip seal installation, and quality control. The results indicate that the installation method was carried out systematically in accordance with the project specifications. The application of D13 chemical anchors improved the structural connection between the expansion joint system and the existing bridge structure, while rapid-setting grout accelerated construction and enabled timely traffic reopening. In addition, the achieved zero-elevation condition enhanced driving comfort and minimized impact loads on the bridge deck. Overall, the implemented installation method provides an effective solution for bridge preservation projects requiring durable and efficient strip seal expansion joint systems.
METODE PELAKSANAAN PEKERJAAN PIERTABLE MENGGUNAKAN SISTEM BRACKET CONSOLE PADA JEMBATAN JUNCTION SEDYATMO TOL KATARAJA SEKSI 1 DIVISI INFRASTRUKTUR 1 DI KOTA JAKARTA UTARA, PROVINSI DKI JAKARTA Nurmala Dwiani; Erni Sari Lumban Toruan
SEMINAR TEKNOLOGI MAJALENGKA (STIMA) Vol 10 (2026)
Publisher : Universitas Majalengka

Show Abstract | Download Original | Original Source | Check in Google Scholar

Abstract

The development of toll road infrastructure plays an important role in improving regional connectivity, facilitating transportation, and supporting national economic growth. In bridge construction, particularly at junction areas with high elevations and limited working space, an effective and safe construction method is essential. The piertable, which connects the pier to the bridge superstructure, requires high construction accuracy. This study aims to describe the installation of the bracket console system, the implementation of piertable construction, and the challenges encountered during the construction process. The study was conducted through direct field observations, interviews and technical discussions with engineers and project supervisors, and a review of project documents, including working drawings and construction methods. The results show that the bracket console system provided stable and safe support for formwork and fresh concrete at an elevation of 13 m. The piertable construction was carried out systematically through reinforcement, formwork installation, concrete casting, curing, and prestressing in accordance with project specifications. Challenges such as reinforcement congestion, strand elongation deviation, and weather conditions were successfully addressed through proper supervision and quality control. Overall, the application of the bracket console system proved to be effective in improving construction efficiency, ensuring work safety, and maintaining the structural quality of the piertable.