METODE PELAKSANAAN PEMASANGAN PCI GIRDER PADA JEMBATAN COLLECTOR ROW-15 KOTA BARU PARAHYANGAN Manu Imarwan; Yayat Hendrayana
SEMINAR TEKNOLOGI MAJALENGKA (STIMA) Vol 10 (2026)
Publisher : Universitas Majalengka

Show Abstract | Download Original | Original Source | Check in Google Scholar

Abstract

This paper discusses the implementation of Prestressed Concrete I-Girder (PCI Girder) installation on the Collector ROW-15 Bridge project in Kota Baru Parahyangan, West Bandung Regency. The bridge was developed to support connectivity within the growing residential area, with PCI Girder selected as the superstructure due to its high strength, consistent precast quality, and efficient installation process. This study aims to describe the installation stages, identify technical and non-technical factors influencing the work, and evaluate the effectiveness of the applied method in terms of quality, time, and safety. The research employed a field study combined with a literature review through direct observation, documentation, and interviews with the site engineer and contractor personnel. The installation process included truss launcher assembly, girder lifting using a mobile crane, manual launching across the truss launcher, and final placement on the bearing pad at the abutment. The findings indicate that the PCI Girder was installed according to the planned alignment and elevation without significant deviation. The main challenges consisted of adverse weather conditions and vegetation around the construction site, both of which were successfully managed without affecting the project schedule. Overall, the applied installation method proved effective in ensuring construction quality, schedule performance, and work safety, making it suitable for bridge projects with similar characteristics