Cost And Productivity Analysis Of Installing 40 X 60 X 120 U-Ditches Using Heavy Equipment Compared To Manual Methods In Sumur Welut, Lakarsantri District, Surabaya: Analisis Biaya Dan Produktivitas Pemasangan U-Ditch 40 X 60 X 120 Menggunakan Alat Berat Dibandingkan Metode Manual Di Sumur Welut, Kec. Lakarsantri, Surabaya Fila Atma Jalu Eka Irawan; Atik Wahyuni
Indonesian Journal of Innovation Studies Vol. 27 No. 2 (2026): April
Publisher : Universitas Muhammadiyah Sidoarjo

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.21070/ijins.v27i2.2438

Abstract

General Background Drainage infrastructure development plays a crucial role in mitigating hydrometeorological disasters and supporting sustainable urban resilience in metropolitan areas like Surabaya. Specific Background The installation of precast concrete U-ditches is widely implemented in urban drainage projects, yet contractors frequently face strategic dilemmas when choosing between manual labor and heavy equipment methods. Knowledge Gap Although mechanical methods are generally assumed to be superior, detailed empirical evaluations comparing direct costs and work productivity per unit between manual and heavy equipment approaches under identical field conditions remain limited. Aims This study aims to analyze and compare work productivity, direct costs, and cost efficiency between the heavy equipment method utilizing an excavator and forklift and the manual method for installing 40 x 60 x 120 cm U-ditches in the Sumur Welut drainage project, Surabaya. Results Field evaluations indicate that the heavy equipment method achieves a daily productivity of 18 units, which is significantly higher than the 2.5 units achieved by the manual method, while yielding a direct cost of Rp 221,667 per unit that proves more economical and time-saving. Novelty This research provides empirical evidence that mechanization successfully compensates for higher daily investment through economies of scale and accelerated schedule completion in urban drainage construction. Implications The findings serve as a reliable quantitative reference for project managers and planners in selecting optimal construction methods to enhance time and cost efficiency in similar infrastructure projects. Key Findings Highlights The heavy equipment method achieves a daily productivity of 18 units, significantly outperforming the manual method's 2.5 units. Mechanized U-ditch installation provides superior time efficiency, reducing project duration from twelve days down to six working days. Despite higher initial daily equipment rental expenses, high-volume production makes the mechanized approach highly cost-effective per unit. Keywords Cost Analysis, Productivity, U-ditch, Heavy Equipment, Manual Method
Drainage System Planning for RSGM Muhammadiyah Sidoarjo: Perencanaan Sistem Drainase RSGM Muhammadiyah Sidoarjo Syafi'ah Raidah Arman; Atik Wahyuni
Procedia of Engineering and Life Science Vol. 10 No. 1 (2026): Proceedings of the 9th Seminar Nasional Sains 2026
Publisher : Universitas Muhammadiyah Sidoarjo

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.21070/bsmcgz34

Abstract

General Background The establishment of the Dental and Oral Hospital (RSGM) of Universitas Muhammadiyah Sidoarjo (UMSIDA) serves as a strategic initiative to advance healthcare quality and clinical education. Specific Background This development alters land use from open spaces to built areas, triggering higher surface runoff that risks waterlogging if not supported by proper drainage. Knowledge Gap Existing drainage networks require rigorous evaluation to determine their capacity to accommodate fluctuating runoff volumes driven by structural expansion. Aims This study aims to evaluate drainage capacity, analyze runoff changes, and recommend safe, effective, and sustainable drainage networks for the hospital area. Results Hydrological and hydraulic computations confirm that the planned U-ditch concrete channels yield a capacity of 0.537〖" m" 〗^3 "/s" , successfully accommodating design discharge values ranging from 0.015〖" m" 〗^3 "/s"  to 0.061〖" m" 〗^3 "/s" . Novelty The integration of Thiessen polygon spatial distribution with normal frequency analysis and hydraulic U-ditch routing optimizes institutional stormwater management. Implications These engineered drainage recommendations prevent local inundation while preserving environmental balance and uninterrupted medical facility operations.  Key Findings Highlights - Normal distribution frequency analysis accurately establishes 5-year return period rainfall parameters for regional drainage planning. - Planned U-ditch concrete channels exhibit a hydraulic discharge capacity of 0.537〖" m" 〗^3 "/s" , thoroughly outperforming peak runoff projections. - Structured stormwater management successfully prevents surface waterlogging and safeguards surrounding environmental equilibrium. Keywords Dental And Oral Hospital, Drainage Study, Surface Runoff, Drainage System, Land Use Change  
Implementation of Weekly Opname Report on UPVC Roof Dismantling and Installation Work at PT Hansa Pratama: Implementasi Laporan Opname Mingguan pada Pekerjaan Pembongkaran dan Pemasangan Atap UPVC di PT Hansa Pratama Arjuna Tri Prasetya; Atik Wahyuni
Procedia of Engineering and Life Science Vol. 10 No. 1 (2026): Proceedings of the 9th Seminar Nasional Sains 2026
Publisher : Universitas Muhammadiyah Sidoarjo

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.21070/p2qe7j91

Abstract

General Background Weekly progress reporting serves as an essential component of construction project management to ensure effective supervision and enhanced work quality. Specific Background Evaluating the implementation of weekly opname reports during UPVC roof dismantling and installation work at PT Hansa Pratama provides critical operational insights. Knowledge Gap Although periodic monitoring is recognized in construction, detailed field evaluations regarding how weekly opname reporting identifies work volume discrepancies and aids scheduling coordination require further documentation. Aims This study assesses the effectiveness of weekly reporting in identifying work volume variances, improving field team coordination, and maximizing project completion efficiency. Results Findings indicate that utilizing weekly opname reports facilitates early variance detection between actual and planned work volumes, increases progress transparency, and accelerates decision-making for resource allocation. Novelty A targeted evaluation framework is established by linking weekly progress opname metrics directly to industrial UPVC roof dismantling and replacement workflows. Implications Implementing structured weekly reporting significantly improves project control and serves as a recommended standard practice for comparable construction projects. Key Findings Highlights Weekly progress reporting enables early detection of variances between actual and planned construction volumes. Systematic opname documentation increases project transparency and facilitates rapid scheduling decisions. Regular performance tracking prevents work delays and enhances team accountability during roof installation. Keywords Weekly reporting, Project monitoring, UPVC roof installation, Project management, Construction efficiency