Journal : RACIC : Rab Construction Research

ANALISIS BI AYA DAN WAKTU DENGAN METODE EARNED VALUE CONCEPT PADA PROYEK BJDM AREA RL CONSTRUCTION AT WELL 3S-21B AREA 9 PT. ADHI KARYA CS WORK UNIT RATE PACKAGEA – DURI Fitra Ramdhani
Racic : Rab Construction Research Vol 1 No 01 (2016): Terbitan pertama Bulan Juni 2016
Publisher : LPPM Universitas Abdurrab

Show Abstract | Download Original | Original Source | Check in Google Scholar | Full PDF (1153.091 KB)

Abstract

Seiring dengan perkembangan sektor migas di Indonesia yang terus berkembang dan dituntut produksi yang tinggi tiap tahunnya, dibutuhkan perencanaan, pelaksanaan serta pengendalian proyek yang serius sehingga mendapatkan hasil yang diinginkan. Dalam pelaksanaan suatu proyek bisa mengalami keterlambatan, percepatan, ataupun tepat waktu sesuai jadwal rencana proyek. Dari segi biaya pelaksanaan suatu proyek bisa mengalami kerugian ataupun keuntungan. Di dalam Konsep Nilai Hasil (Earned Value Concept) akan dikaji untuk meramalkan apakah waktu penyelesaian proyek sesuai dengan rencana awal jadwal proyek dalam setiap periode pelaporan dan seberapa besar keuntungan ataupun kerugian di akhir proyek. Metode Konsep Nilai Hasil (Earned Value Concept) adalah suatu metode pengendalian yang digunakan untuk mengendalikan biaya dan jadwal proyek. Metode ini memberikan informasi Varian Biaya (Cost Varians), Varian Jadwal (Schedule Varians), Indeks Kinerja Biaya (Cost Performance Index), Indek Kinerja Jadwal (Schedule Performance Index) proyek pada suatu periode pelaporan. Dari metode ini didapatkan juga informasi prediksi besaran biaya dan lamanya waktu untuk penyelesaian seluruh pekerjaan berdasarkan indikator kinerja saat pelaporan. EVC (Earned Value Concept) dapat meramalkan biaya akhir dan waktu penyelesaian proyek lebih dini pada setiap periode waktu pelaporan. Pada Proyek Pembangunan Well Program ini, Selama pelaksanaan proyek dari minggu ke-1 sampai dengan minggu ke-16 tidak terjadi deviasi progress antara rencana jadwal proyek dengan pelaksanaan proyek (tepat waktu) Proyeksi akhir biaya mengalami keuntungan sebesar Rp. 134.724.718,.77 dan proyek akan selesai dalam 155 hari kalender, sehingga pelaksanaan pekerjaan ini sesuai jadwal yang telah ditentukan.
PERENCANAAN RUTE JARINGAN LINTAS ANGKUTAN BARANG DI KOTA PEKANBARU DENGAN APLIKASI PTV VISUM Rahmat Tisnawan; Fitra Ramdhani; Muhammad Rifky Ariansyah
Racic : Rab Construction Research Vol 6 No 2 (2021): Desember
Publisher : LPPM Universitas Abdurrab

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.36341/racic.v6i2.2196

Abstract

The increase in freight movement in Pekanbaru is not followed by the development of good freight transport facility, causing traffic creasing caused by mixtraffic, thus degrading the performance of road segments in Pekanbaru City. It demands the need for the preparation of more effective and efficient freight transport facilities. In an effort to improve the performance of the road segment, several handling scenarios are implemented by cross network arrangement and capacity building of road segments crossed by freight transport. To know the performance of the road segment, the burden of each handling scenario, including in plan year 2030. Based on the result of the loading analysis, it is found that the scenario of ring road construction and road network of freight transport shows the improvement of road performance, where the speed in the base year 33.43 km / hour increases to 40.02 km / h in 2025 and becomes 39.41 km / hr.
PEMANFAATAN ABU SERBUK KAYU DAN SEMEN PORTLAND SEBAGAI FILLER PADA CAPURAN ASPHALT CONCRETE -WEARING COURSE DONI RINALDI BASRI; Fitra Ramdhani; Faridhotul Apriliya Wardani
Racic : Rab Construction Research Vol 7 No 2 (2022): DESEMBER
Publisher : LPPM Universitas Abdurrab

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.36341/racic.v7i2.3066

Abstract

Waste from wood processing is often found in Pekanbaru City, so it needs to be utilized. This research utilizes sawdust and portland cement as alternative materials to replace filler in the manufacture of Asphalt Concrete-Wearing Course (AC-WC) mixture. The purpose of this study was to determine the characteristics of the Marshall test on the AC-WC layer using a combination of sawdust and Portland cement filler. The method used is laboratory experiments with the initial step of finding the KAO value (Optimum Asphalt Content) with fillers using rock ash. Followed by replacing the filler with a combination of sawdust and portland cement. Variations in the mixture of Portland cement and sawdust, namely 0%-0%, 15%-85%, 25%-75%, 30%-70%, 40%-60%, 50%-50%, and 100% -0%. The specifications used in this study are the 2018 Revision 2 Public Road Specifications. The KOA obtained is 5.5%. Then the Marshall test was carried out on each variation to get the stability value and the mixed density value. Marshall test results with the best filler variations in this study were 60% sawdust and 40% portland cement. It can be seen that based on the stability value of the composition, the highest stability value was 1,278.64 kg, the MQ value was 491.78 kg/mm ​​and the melting value was 2.60 mm so it was concluded that the best AC-WC quality in this study found filler variations. 40% portland cement and 60% sawdust.
ANALISA REOLOGI DASAR ASPAL MODIFIKASI NANO ABU CANGKANG SAWIT Fitra Ramdhani; Bambang Sugeng Subagio; Harmein Rahman; Russ Bona Frazila
Racic : Rab Construction Research Vol 8 No 2 (2023): DESEMBER
Publisher : LPPM Universitas Abdurrab

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.36341/racic.v8i2.4216

Abstract

Pengembangan aspal modifikasi dengan menggunakan nano teknologi merupakan salah satu inovasi dalam menciptakan sebuah material baru yang berskala nano meter yang mempunyai sifat lebih unggul dari material yang berukuran besar. Keunikan dari nano material yaitu semakin kecil ukuran material maka luas permukaan dan kinerja karakteristik material dalam campuran aspal semakin meningkat. Penelitian ini bertujuan untuk mengetahui pengaruh dari penambahan Nano Abu Cangkang Sawit (NACS) pada bitumen terhadap sifat reologi dasar aspal.. Metode penelitian menggunakan metode pengujian di laboratorium. Material nano yang digunakan adalah material abu cangkang sawit yang diperoleh dari limbah sisa pembakaran cangkang sawit yang berasal dari Riau yang kemudian diproses menjadi Nano Abu Cangkang Sawit (NACS) di laboratorium Kimia ITB. Aspal yang digunakan yaitu aspal Pen 60/70 produksi Pertamina. Penggunaan material NACS dalam modifikasi aspal dengan variasi 1%, 2%, dan 3% NACS dapat menurunkan nilai penetrasi ,meningkatkan titik lembek, menurunkan nilai daktilitas dan menurunkan suhu pencampuran dan suhu pemadatan seiring dengan bertambahnya persentase NACS.. Kata-kata Kunci: Nano Abu Cangkang Sawit (NACS), reologi dasar aspal, Nano teknologi